Requesting authorization for SCP to award a construction contract for the Willowridge Levee Improvements - Phase III, State Project No. H.009257, through the State of LA DOTD under the Louisiana Statewide Flood Control Program
|
Type:
|
Resolution
|
Status:
|
Approved
|
On agenda:
|
9/8/2015
|
Final action:
|
9/8/2015
|
Enactment date:
|
|
Enactment #:
|
6178
|
Title:
|
A resolution requesting authorization for St. Charles Parish to award a construction contract for the Willowridge Levee Improvements - Phase III, State Project No. H.009257, through the State of Louisiana Department of Transportation and Development (DOTD) under the Louisiana Statewide Flood Control Program.
|
Indexes:
|
Floods, Highway Dept., Hurricane Protection Levee (WB - Willowridge, Ph. III)
|
Related files:
|
2017-0227, 2015-0340, 2013-0262, 2008-0418, 2015-0315, 2018-0159, 2011-0257, 2012-0294, 2013-0408, 2014-0279, 2015-0104, 2015-0105, 2015-0108, 2015-0116, 1999-5052, 2000-0144, 2000-0241, 2000-0242, 2000-0243, 2008-0211, 2008-0212, 2010-0318, 2013-0407, 2011-0057, 2011-0058, 2011-0088, 2011-0233, 2012-0081, 2015-0109, 2016-0076, 2013-0411, 2014-0084, 2015-0106, 2015-0146, 2015-0205, 2015-0234, 2015-0308, 2017-0354, 2018-0226, 2020-0081, 2020-0082, 2020-0083
|
2015-0309
INTRODUCED BY: V.J. ST. PIERRE, JR., PARISH PRESIDENT
(GRANTS OFFICE)
ST. CHARLES PARISH COUNCIL
RESOLUTION NO.
Title
A resolution requesting authorization for St. Charles Parish to award a construction contract for the Willowridge Levee Improvements - Phase III, State Project No. H.009257, through the State of Louisiana Department of Transportation and Development (DOTD) under the Louisiana Statewide Flood Control Program.
Body
WHEREAS, St. Charles Parish has received bids on August 25, 2015, at 10:00 a.m. on the Willowridge Levee Improvements - Phase III flood control project under the Statewide Flood Control Program; and,
WHEREAS, Burk-Kleinpeter, Inc., Suresh I. Shah, P.E., the Consulting Engineer, has recommended that award of the contract be made to the lowest qualified bidder, Sealevel Construction, Inc., for the Base Bid in the amount of $7,440,171.00.
NOW, THEREFORE, BE IT RESOLVED, BY THE MEMBERS OF THE ST. CHARLES PARISH COUNCIL, acting pursuant to the recommendation of Burk-Kleinpeter, Inc., Suresh I. Shah, P.E., the Consulting Engineer, that the Base Bid in the amount of $7,440,171.00 by Sealevel Construction, Inc., be accepted and a construction contract be awarded to them for the Willowridge Levee Improvements - Phase III, State Project No. H.009257.
The foregoing resolution having been submitted to a vote, the vote thereon was as follows:
And the resolution was declared adopted this day of , 2015, to become effective five (5) days after publication in the Official Journal.