2000-0307
INTRODUCED BY: ALBERT D. LAQUE, PARISH PRESIDENT
(DEPARTMENT OF WATERWORKS)
ORDINANCE NO.___________
Title
An ordinance to approve and authorize the execution of Change Order No. 1 and final for the Generator Building and Foundation to increase the contract time by 34 calendar Days.
Body
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Ordinance No. 99-8-16 adopted August 16, 1999, by the St. Charles Parish Council, approved and authorized the execution of a contract with Picciola Construction Company, Inc. for the Generator Building and Foundation in the amount of $200,300.00 and,
SECTION II. That it is necessary to increase the contract time by 34 days.
NOW, THEREFORE, BE IT ORDAINED, THAT WE, THE MEMBERS OF THE ST. CHARLES PARISH COUNCIL, do hereby approve and authorize the execution of Change Order No. One (1) and final for the Generator Building and Foundation to increase the contract time by 34 Calendar Days.
BE IT FURTHER ORDAINED, that the Parish President is hereby authorized to execute this Change Order to the contract.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this____ day of ______, 2000, to become effective five (5) days after publication in the Official Journal.
CHAIRMAN:
SECRETARY:
DLVD/PARISH PRESIDENT:
APPROVED: DISAPPROVED:
PARISH PRESIDENT:
RETD/SECRETARY:
AT: RECD BY: