File #: 2020-0042    Version: 1 Name: Change Order No. 1 (Final) for Parish Project No. P080502-18A, Oak Street Pump Station Improvements
Type: Ordinance Status: Enacted
File created: 2/3/2020 In control: Parish Council
On agenda: 2/17/2020 Final action: 2/17/2020
Enactment date: Enactment #: 20-2-3
Title: An ordinance approving and authorizing the execution of Change Order No. 1 (Final) for Parish Project No. P080502-18A, Oak Street Pump Station Improvements, to balance the contract quantities with actual quantities resulting in a decrease of $103,895.00 in contract price and an increase in the contract time by 42 days.
Sponsors: Matthew Jewell, Department of Public Works
Indexes: DRO (Oak Street Pump Station Imp.), Public Works (Dept. of)
Attachments: 1. 2020-0042 Change Order No. 1 Oak Street PS Improvements, 2. 2020-0042 Final Ord 20-2-3 with change order
Related files: 2019-0164, 2019-0098, 2014-0016, 2015-0008, 2015-0009, 2015-0087, 2008-0249, 2008-0482, 2010-0414, 2011-0201, 2011-0354, 2013-0002, 2013-0157, 2014-0001, 2012-0076, 2012-0186, 2012-0297, 2018-0342, 2020-0177, 2024-0018, 2012-0361

2020-0042

INTRODUCED BY:                     MATTHEW JEWELL, PARISH PRESIDENT

                     (DEPARTMENT OF PUBLIC WORKS)

ORDINANCE NO.                                                                 

Title

An ordinance approving and authorizing the execution of Change Order No. 1 (Final) for Parish Project No. P080502-18A, Oak Street Pump Station Improvements, to balance the contract quantities with actual quantities resulting in a decrease of $103,895.00 in contract price and an increase in the contract time by 42 days.

Body

WHEREAS,                     St. Charles Parish awarded a contract to Sealevel Construction, Inc. with a contract price of $1,062,870.00 and a contract time of 240 days; and,

WHEREAS,                     the contract is substantially complete; and,

WHEREAS,                     it is necessary to amend the contract resulting in a decrease in the contract price by $103,895.00 and an increase in the contract time by 42 days as shown on the Change Order form.

THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:

SECTION I.                     That Change Order No. 1 (Final) for Parish Project No. P080502-18A, Oak Street Pump Station Improvements, to decrease the contract price by $103,895.00 and increase the contract time by 42 days is hereby approved and accepted.

SECTION II.                     That the Parish President is hereby authorized to execute said change order on behalf of the Parish of St. Charles.

The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:

 

 

 

 

And the ordinance was declared adopted this               day of                     , 2020, to become effective five (5) days after publication in the Official Journal.

 

 