File #: 2021-0191    Version: 1 Name: Change Order No. 1 (final) for the East Bank Transmission Line Repair/Replacement Project No. WWKS 101
Type: Ordinance Status: Enacted
File created: 7/26/2021 In control: Parish Council
On agenda: 8/9/2021 Final action: 8/9/2021
Enactment date: Enactment #: 21-8-2
Title: An ordinance approving and authorizing the execution of Change Order No. 1 (final) for the East Bank Transmission Line Repair/Replacement Project No. WWKS 101 to increase the contract amount by $130,590.28, and to increase the contract time by one hundred sixty (160) days.
Sponsors: Matthew Jewell, Department of Waterworks
Indexes: WW (EB Transmission Line Repair/Replacement)
Attachments: 1. 2021-0191 change order, 2. 2021-0191 Final Ord 21-8-2 with change order
Related files: 2020-0138, 2019-0143
2021-0191
INTRODUCED BY: MATTHEW JEWELL, PARISH PRESIDENT
(DEPARTMENT OF WATERWORKS)
ORDINANCE NO.
Title
An ordinance approving and authorizing the execution of Change Order No. 1 (final) for the East Bank Transmission Line Repair/Replacement Project No. WWKS 101 to increase the contract amount by $130,590.28, and to increase the contract time by one hundred sixty (160) days.
Body
WHEREAS, Ordinance No. 20-6-5 adopted June 1, 2020 by the St. Charles Parish Council, approved and authorized the execution of a contract with Wallace C. Drennan, Inc. for the East Bank Transmission Line Repair/Replacement Project No. WWKS 101 in the amount of $433,000.00; and,
WHEREAS, Change Order No.1 (final) is a result of changes within the contract to eliminate the mechanical cleaning item (as it was used) and adds the extra costs for the project due to CN Railroad (Illinois Central Railroad Co.) safety requirements (including extra insurance, flagging expenses, and work downtime due to passing trains; and,
WHEREAS, the increase in contract amount by $130,590.28 is a result of an increase of $100,078.75 for CN Railroad ROE and Flagger costs, an increase of $32,511.53 for railroad downtime for labor and equipment, and a decrease of $2,000.00 for eliminating mechanical cleaning/descaling; and,
WHEREAS, the increase in contract time by one hundred sixty (160) calendar days is a result of Wallace C. Drennan, Inc.'s work downtime due to passing trains.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. 1 (final) for the East Bank Transmission Line Repair/Replacement Project No. WWKS 101 to increase the contract amount by $130,590.28, and to increase the contract time by one hundred sixty (160) days is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.