2012-0297
INTRODUCED BY: V. J. ST. PIERRE, JR, PARISH PRESIDENT
WENDY BENEDETTO, COUNCILWOMAN, DISTRICT III
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.
Title
An Emergency Ordinance to approve and authorize the execution of a Contract with Cycle Construction Co., LLC for Parish Project No. P080502-5 the Carriage Canal Bank Repairs Project in Destrehan.
Body
WHEREAS, a section of the Carriage Canal Bank has clasped into the Canal obstructing drainage in the area and endangering the stability of the adjourning buildings; and,
WHEREAS, emergency sealed bids were received by St. Charles Parish on August 13, 2012 for Parish Project P080502-5 Carriage Canal Bank Repairs; and,
WHEREAS, Evens Graves Engineers, Inc., the Engineer for the Project, has reviewed the bids and recommended that the low bid of Cycle Construction Co., LLC in the amount of $558,810.00 be accepted; and,
WHEREAS, it is the desire of the Parish Council to approve said Emergency Contract.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That a Public Emergency is hereby declared for the Carriage Canal Bank Repairs Project.
SECTION II. That the bid of Cycle Construction Co., LLC for the Carriage Canal Bank Repairs Project, Project No. P080502-5 in the amount of $ 558,810.00 is hereby approved and accepted.
SECTION III. That the Parish President is hereby authorized to execute said Emergency Contract on behalf of the Parish of St. Charles.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this day of , 2012, to become effective immediately upon adoption.