logo  ST. CHARLES PARISH, LA
File #: 2005-0200    Version: 1 Name: C.O. 1 - Final for PW Drainage Telemetry - Phase IIIA Kellogg Pump Station, to decrease the contract amount by $2,095.00 and to increase the contract time by 49 calendar days
Type: Ordinance Status: Enacted
File created: 7/11/2005 In control: Parish Council
On agenda: Final action: 8/1/2005
Enactment date: 8/1/2005 Enactment #: 05-8-2
Title: An ordinance approving and authorizing the execution of Change Order No. One (1) - Final for Parish Project No. P000303A, Parish Wide Drainage Telemetry - Phase IIIA Kellogg Pump Station, to decrease the contract amount by $2,095.00 and to increase the contract time by 49 calendar days.
Sponsors: Albert D. Laque, Department of Public Works
Indexes: DRO (Telemetry Ph. IIIA, Kellogg Pump Station)
Attachments: 1. 2005-0200 Change Order-F, 2. 2005-0200 Final Ord 05-8-2 with Change Order
Related files: 2000-0282, 2001-0010, 2004-0284, 2004-0285, 2004-0286, 2005-0225, 2001-0218, 2001-0247, 2001-0444, 2003-0123, 2005-0224, 2022-0195
2005-0200
INTRODUCED BY:      ALBERT D. LAQUE, PARISH PRESIDENT
                  (DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.                   
Title
An ordinance approving and authorizing the execution of Change Order No. One (1) - Final for Parish Project No. P000303A, Parish Wide Drainage Telemetry - Phase IIIA Kellogg Pump Station, to decrease the contract amount by $2,095.00 and to increase the contract time by 49 calendar days.
Body
WHEREAS,      Ordinance No. 04-8-7 adopted August 2, 2004 by the St. Charles Parish Council approved and authorized the execution of a contract with Entergy Operation Services, Inc. for the construction of the Parish Wide Drainage Telemetry - Phase IIIA Kellogg Pump Station, Parish Project No. P000303A, in the amount of $123,443.00; and,
WHEREAS,      it is necessary to decrease the original contract in the amount of $2,095.00 and to increase the contract time by 49 calendar days to balance actual quantities.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I.      To approve and authorize the execution of Change Order No. One (1) - Final for Parish Project No. P000303A, Parish Wide Drainage Telemetry - Phase IIIA Kellogg Pump Station, to decrease the contract amount by $2,095.00 and to increase the contract time by 49 calendar days.
SECTION II.      That the Parish President is hereby authorized to execute said Change Order.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
 
 
 
 
And the ordinance was declared adopted this            day of                       , 2005, to become effective five (5) days after publication in the Official Journal.
Kellogg Pump Station C.O. Phase IIIA
 
 
 
 
 