File #: 2011-0358    Version: 1 Name: Change Order No. 1(Final) for Parish Project No. P090204 Ormond Boulevard Culvert Replacement
Type: Ordinance Status: Enacted
File created: 11/7/2011 In control: Parish Council
On agenda: Final action: 11/21/2011
Enactment date: 11/21/2011 Enactment #: 11-11-17
Title: An ordinance approving and authorizing the execution of Change Order No. 1(Final) for Parish Project No. P090204 Ormond Boulevard Culvert Replacement to decrease the contract amount by $110,522.93 and add thirty seven (37) days to the contract time.
Sponsors: V.J. St. Pierre Jr., Department of Public Works
Indexes: DRO (Replace Culverts Crossing Under Ormond Blvd. at Lake No. 5)
Attachments: 1. Ormond Change Order.pdf, 2. 2011-0358 Change Order-F, 3. 2011-0358 Final Ord 11-11-17 with Change Order
Related files: 2009-0081, 2011-0024
2011-0358
INTRODUCED BY: V.J. ST. PIERRE, JR., PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. _____
Title
An ordinance approving and authorizing the execution of Change Order No. 1(Final) for Parish Project No. P090204 Ormond Boulevard Culvert Replacement to decrease the contract amount by $110,522.93 and add thirty seven (37) days to the contract time.
Body
WHEREAS, Ordinance No. 11-1-10, adopted January 24, 2011, by the St. Charles Parish Council, approved and authorized the execution of a contract with Fleming Construction Co., LLC for Parish Project No. P090204 Ormond Boulevard Culvert Replacement in the amount of $1,848,179.00; and,
WHEREAS, The decrease in contract amount resulted from the deletion of two line items in the amount of $222,875.00, adding five line items in the amount of $16,698.10, and changing thirty three line items with a net reduction of $95,653.97: and,
WHEREAS, The increase in contract time resulted from twenty seven days related to weather and 10 days for the change directive items.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS,
SECTION I. To approve and authorize the execution of Change Order No. 1(Final) for Parish Project No. P090204 Ormond Boulevard Culvert Replacement to decrease the contract amount by $110,522.93 and increase the contract time by thirty seven (37) days.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:




And the ordinance was declared adopted this _____ day of ___________, 2011,
to become effective five (5) days after publication in the Official Journal.



CHAIRMAN:______________________________________________
SECRETARY:_____________________________________________
DLVD/PARISH PRESIDENT:_________________________________
APPROVED:______________ DISAPPROVED:__________________

PARISH PRESIDENT:_...