logo  ST. CHARLES PARISH, LA
File #: 2011-0357    Version: 1 Name: Change Order No. 1 for Parish Project No. S080501-6, Destrehan Regional WWTP H2S System & Secondary Wet Well
Type: Ordinance Status: Enacted
File created: 11/7/2011 In control: Parish Council
On agenda: Final action: 11/21/2011
Enactment date: 11/21/2011 Enactment #: 11-11-16
Title: An ordinance approving and authorizing the execution of Change Order No. 1 for Parish Project No. S080501-6, Destrehan Regional WWTP H2S System & Secondary Wet Well to increase the contract amount by $49,869.00 and add 38 days to the contract time.
Sponsors: V.J. St. Pierre Jr., Department of Wastewater
Indexes: SPW (Destrehan TP H2S Sys. and Secondary Wet Well)
Attachments: 1. Destrehan Change Order No One.pdf, 2. 2011-0357 Change Order-F, 3. 2011-0357 Final Ord 11-11-16 with Change Order
Related files: 2009-0306, 2010-0414, 2009-0331, 2011-0354, 2009-0244, 2012-0076, 2012-0185, 2008-0455, 2011-0201, 2010-0413, 2009-0100, 2008-0441
2011-0357
INTRODUCED BY: V.J. ST. PIERRE, JR., PARISH PRESIDENT
(DEPARTMENT OF WASTEWATER)
ORDINANCE NO. _____
Title
An ordinance approving and authorizing the execution of Change Order No. 1 for Parish Project No. S080501-6, Destrehan Regional WWTP H2S System & Secondary Wet Well to increase the contract amount by $49,869.00 and add 38 days to the contract time.
Body
WHEREAS, Ordinance No. 10-12-6, adopted December 6, 2010, by the St. Charles Parish Council, approved and authorized the execution of a contract with Max Foote Construction for S080501-6 Destrehan Regional WWTP H2S System & Secondary Wet Well in the amount of $1,070,000.00; and,
WHEREAS, The majority of the cost associated with this change order is due to the replacement of approximately 75 ft of severely corroded 18 in force main feeding the inlet well and relocation of the inlet feed to the new secondary wet well to avoid an electrical duct bank; and,
WHEREAS, It is necessary to amend the contract revising three items resulting in an increase to the contract amount by $49,869.00 and increasing the contract time by 38(thirty eight) days.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS,
SECTION I. To approve and authorize the execution of Change Order No. 1 for Parish Project No. S080501-6, Destrehan Regional WWTP H2S System & Secondary Wet Well to increase the contract amount by $49,869.00 and contract time by 38 days.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:




And the ordinance was declared adopted this ______ day of ___________, 2011
to become effective five (5) days after publication in the Official Journal.



CHAIRMAN:______________________________________________
SECRETARY:_____________________________________________
DLVD/PARISH PRESIDENT:_________________________________
APPROVED:...

Click here for full text