File #: 2011-0391    Version: 1 Name: Contract with Gilmore & Son Construction Corporation - Replace Culverts Willowdale and Beaupre Crossings
Type: Ordinance Status: Enacted
File created: 12/5/2011 In control: Parish Council
On agenda: Final action: 12/19/2011
Enactment date: 12/19/2011 Enactment #: 11-12-11 AMENDED
Title: An ordinance to approve and authorize the execution of a contract with Gilmore & Son Construction Corporation for project P090201-4 Replace Culverts Willowdale and Beaupre Crossings in the amount of $312,000.00.
Sponsors: V.J. St. Pierre Jr., Department of Public Works, Shelley Tastet
Indexes: DRO (Replace Culverts Willowdale and Beaupre Crossings)
Attachments: 1. Contract Agreement.pdf, 2. Certified BidTab for Willowdale and Beaupre 12-2-11.pdf, 3. 2011-0391 Contract-F, 4. 2011-0391 Final Ord 11-12-11 with Contract, 5. 2011-0391 Completion-F
Related files: 2009-0078, 2012-0385, 2018-0334, 2018-0181, 2017-0367, 2017-0158, 2016-0246
2011-0391
INTRODUCED BY:       V.J. ST. PIERRE, JR., PARISH PRESIDENT
                   (DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. __________
Title
An ordinance to approve and authorize the execution of a contract with Gilmore & Son Construction Corporation for project P090201-4 Replace Culverts Willowdale and Beaupre Crossings in the amount of $312,000.00.
Body
WHEREAS,      sealed bids were received by St. Charles Parish on December 1, 2011, for project P090201-4 Replace Culverts Willowdale and Beaupre Crossings; and,
WHEREAS,      Professional Engineering and Environmental Consultants, Inc. PEEC, the Engineer for the Project, has reviewed the bids and recommended that the contract be awarded to the low bidder, Gilmore & Son Construction Corporation in the amount of $312,000.00; and,
WHEREAS,      this project also has an approved FEMA Hazard Mitigation Grant in the amount of $549,275.00 to assist the Parish in project funding.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
      SECTION I.  That the bid of Gilmore & Son Construction Corporation for the construction of project P090201-4 Replace Culverts Willowdale and Beaupre Crossings, is hereby approved and accepted in the amount of $312,000.00.
      SECTION II.  That the Parish President is hereby authorized to execute said contract on behalf of St. Charles Parish.
Vote
      The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
 
 
 
 
      And the ordinance was declared adopted this ______ day of __________, 2011,
to become effective five (5) days after publication in the Official Journal.
 
 
 
CHAIRMAN:______________________________________________
SECRETARY:_____________________________________________
DLVD/PARISH PRESIDENT:_________________________________
APPROVED:______________ DISAPPROVED:__________________
 
PARISH PRESIDENT:______________________________________
RETD/SECRETARY:_______________________________________
AT:_______________RECD BY: _____________________________