File #: 2015-0311    Version: 1 Name: C.O. No. 2 (Final) for Project No P081102-5, Dunleith Canal Stabilization Phase 4, to balance the contract quantities with actual quantities resulting in a decrease of $50,400.00 and decrease of 13 days
Type: Ordinance Status: Enacted
File created: 9/8/2015 In control: Parish Council
On agenda: 9/21/2015 Final action: 9/21/2015
Enactment date: Enactment #: 15-9-12
Title: An ordinance approving and authorizing the execution of Change Order No. 2 (Final) for Parish Project No P081102-5, Dunleith Canal Stabilization Phase 4, to balance the contract quantities with actual quantities resulting in a decrease of $50,400.00 and decrease of 13 days.
Sponsors: V.J. St. Pierre Jr., Department of Public Works
Indexes: DRO (Dunleith Canal Stab., Ph. 4), Public Works (Dept. of)
Attachments: 1. 2015-0311 Dunleith Phase IV - revised Change Order No. 2 Final for Introduction, 2. 2015-0311 Change Order-F, 3. 2015-0311 Final Ord 15-9-12 with Change Order
Related files: 2015-0241, 2015-0150, 2003-0025, 2003-0199, 2014-0402, 2015-0049, 2000-0505, 2001-0219, 2002-0396, 2011-0296, 2012-0211, 2012-0418, 2013-0211, 2014-0348, 2008-0481, 2010-0277, 2011-0021, 2020-0101, 2017-0216, 2016-0247, 2018-0066, 2019-0265, 2019-0347, 2015-0339, 2016-0299, 2020-0313

2015-0311

INTRODUCED BY:                     V.J. St. Pierre, JR., PARISH PRESIDENT

                                                               (DEPARTMENT OF PUBLIC WORKS)

ORDINANCE NO.                                                                 

Title

An ordinance approving and authorizing the execution of Change Order No. 2 (Final) for Parish Project No P081102-5, Dunleith Canal Stabilization Phase 4, to balance the contract quantities with actual quantities resulting in a decrease of $50,400.00 and decrease of 13 days.

Body

WHEREAS,                     Ordinance No. 14-12-12 adopted December 15, 2014 by the St. Charles Parish Council awarded construction of Parish Project No P081102-5, Dunleith Canal Stabilization Phase 4, to Circle Construction LLC in the amount of $1,427,563.00; and,

WHEREAS,                     it is necessary to amend the contract resulting in a decrease to the contract amount by $50,400.00 and decrease contract time by 13 days.  Final contract amount will be $1,392,467.62

THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:

                     SECTION I.                     That Change Order No. 2 (Final) for Parish Project No. P081102-5, Dunleith Canal Stabilization Phase 4, to decrease the contract amount by $50,400.00 and decrease the contract time by 13 days is hereby approved and accepted.

                     SECTION II.                     That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.

                     The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:

 

 

 

 

                     And the ordinance was declared adopted this ______ day of __________, 2015, to become effective five (5) days after this publication in the official journal.

 

 