2015-0311
INTRODUCED BY: V.J. St. Pierre, JR., PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.
Title
An ordinance approving and authorizing the execution of Change Order No. 2 (Final) for Parish Project No P081102-5, Dunleith Canal Stabilization Phase 4, to balance the contract quantities with actual quantities resulting in a decrease of $50,400.00 and decrease of 13 days.
Body
WHEREAS, Ordinance No. 14-12-12 adopted December 15, 2014 by the St. Charles Parish Council awarded construction of Parish Project No P081102-5, Dunleith Canal Stabilization Phase 4, to Circle Construction LLC in the amount of $1,427,563.00; and,
WHEREAS, it is necessary to amend the contract resulting in a decrease to the contract amount by $50,400.00 and decrease contract time by 13 days. Final contract amount will be $1,392,467.62
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. 2 (Final) for Parish Project No. P081102-5, Dunleith Canal Stabilization Phase 4, to decrease the contract amount by $50,400.00 and decrease the contract time by 13 days is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this ______ day of __________, 2015, to become effective five (5) days after this publication in the official journal.
CHAIRMAN:
SECRETARY:
DLVD/PARISH PRESIDENT:
APPROVED: DISAPPROVED:
PARISH PRESIDENT:
RETD/SECRETARY:
AT: RECD BY: