logo  ST. CHARLES PARISH, LA
File #: 2013-0281    Version: Name: C.O. No. 1 (final) for Bertucci Contracting Company, LLC, for PO-42 West LaBranche Shoreline Protection Project, Coastal Impact Assistance Program
Type: Ordinance Status: Enacted
File created: 8/5/2013 In control: Parish Council
On agenda: Final action: 8/19/2013
Enactment date: 8/19/2013 Enactment #: 13-8-16
Title: An ordinance approving and authorizing the execution of Change Order No. 1 (final) for Bertucci Contracting Company, LLC, for PO-42 West LaBranche Shoreline Protection Project, Coastal Impact Assistance Program to decrease the construction days by 10 and to increase the contract amount by $10,370.50.
Sponsors: V.J. St. Pierre Jr., Department of Planning & Zoning, Coastal Zone Management Section
Indexes: CZM (West LaBranche Shoreline Protection)
Attachments: 1. 2013-0281 Change Order-F, 2. 2013-0281 Final Ord 13-8-16 with Change Order
Related files: 2012-0282, 2012-0194, 2012-0127, 2012-0080, 2011-0227, 2015-0266, 2015-0201, 2015-0141, 2015-0048, 1999-5065, 2009-0454, 2011-0112, 2008-0442, 2012-0302, 2012-0415, 2014-0205, 2014-0235, 2014-0239, 2015-0027, 2015-0267, 2015-0387, 2015-0384, 2015-0385, 2015-0386, 2015-0388, 2015-0389, 2016-0067
2013-0281
INTRODUCED BY:      V.J. St. Pierre, JR., PARISH PRESIDENT
                  (DEPARTMENT OF PLANNING & ZONING/CZM)
ORDINANCE NO.                    
Title
An ordinance approving and authorizing the execution of Change Order No. 1 (final) for Bertucci Contracting Company, LLC, for PO-42 West LaBranche Shoreline Protection Project, Coastal Impact Assistance Program to decrease the construction days by 10 and to increase the contract amount by $10,370.50.
Body
WHEREAS,      Ordinance No. 12-12-3 adopted December 3, 2012 by the St. Charles Parish Council awarded construction of the West LaBranche Shoreline Protection Project to Bertucci Contracting Company, LLC.; and,
WHEREAS,      Because of site condition changes between the original survey date of May 2010 and the construction start date of February 2013 more rock was required to complete the project.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
      SECTION I.      To approve and authorize the execution of Change Order No. 1 (final) for Bertucci Contracting Company, LLC, for PO-42 West LaBranche Shoreline Protection Project, Coastal Impact Assistance Program to decrease the construction days by 10 and to increase the contract amount by $10,370.50.
      SECTION II.      That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
 
 
 
 
And the ordinance was declared adopted this ______ day of __________, 2013, to become effective five (5) days after this publication in the official journal.
 
 
 