2013-0156
INTRODUCED BY: V.J. ST. PIERRE, JR., PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.
Title
An ordinance to approve and authorize the execution of a Contract by and between the Parish of St. Charles and HHP Construction Group, LLC for 5th Street Sidewalk Extension Norco, Parish Project No. P091101, in the amount of $148,250.00.
Body
WHEREAS, The Safe Routes to School program was designed to install a sidewalk the entire length of 5th Street in Norco; but do to budgetary constraints only the base and alternate #1 were awarded and alternate #2 was not; and,
WHEREAS, St. Charles Parish desires to have the entire sidewalk constructed and asked for bids to construct the remainder (i.e., alternate #2); and,
WHEREAS, sealed bids were received by St. Charles Parish on March 5, 2013 for Project No. P091101, 5th Street Sidewalk Extension Norco; and,
WHEREAS, Civil & Environmental Consulting Engineers, the Engineer for the Project, have reviewed the bids and recommend that the Contract be awarded to the low bidder, HHP Construction Group, LLC, in the amount of $148,250.00.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That the bid of HHP Construction Group, LLC for the construction of Project No. P091101, 5th Street Sidewalk Extension Norco, be hereby approved and accepted, in the amount of $148,250.00.
SECTION II. That the Parish President is hereby authorized to execute said contract documents on behalf of St. Charles Parish.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this day of , 2013, to become effective five (5) days after publication in the Official Journal.
CHAIRMAN:
SECRETARY:
DLVD/PARISH PRESIDENT:
APPROVED: DISAPPROVED:
PARISH PRESIDENT:
RETD/SECRETARY:
AT: RECD BY: