2011-0350
INTRODUCED BY: V.J. ST. PIERRE, JR., PARISH PRESIDENT
(DEPARTMENT OF ANIMAL CONTROL)
ORDINANCE NO.
Title
An ordinance to approve and authorize the execution of Change Order No. 1 for the Animal Shelter at 931 Rue La Cannes in Luling to increase the Contract Time by 17 days and the Contract Amount by $1,032.43.
Body
WHEREAS, the St. Charles Parish Council adopted Ordinance No. 11-6-8 on June 6, 2011 approving and authorizing the execution of a contract with The Gee Cee Company of LA, Inc. for the construction of the Animal Shelter at 931 Rue La Cannes in Luling; and,
WHEREAS, it is necessary to adjust the original contract to reflect those items more fully described in Change Order No. 1, said adjustment as recommended by Campo Designs Architects, Inc. in the amount of a $1,032.43 increase and to increase the Contract Time by 17 days; and,
WHEREAS, it is the desire of the Parish Council to approve said Change Order No. 1.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. 1 for the Animal Shelter in the amount of a $1,032.43 increase and an increase in Contract Time of seventeen (17) days is hereby approved.
SECTION II. That the Parish President is hereby authorized to execute said Change Order No. 1 on behalf of St. Charles Parish.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this day of , 2011, to become effective five (5) days after publication in the Official Journal.
CHAIRMAN:
SECRETARY:
DLVD/PARISH PRESIDENT:
APPROVED: DISAPPROVED:
PARISH PRESIDENT:
RETD/SECRETARY:
AT: RECD BY: