2012-0185
INTRODUCED BY: V.J. ST. PIERRE, JR., PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. _____
Title
An ordinance approving and authorizing the execution of Change Order No. 2(Final) for Parish Project No. S080501-6, Destrehan Regional WWTP H2S System & Secondary Wet Well to decrease the contract amount by $89,747.00 and add 73 days to the contract time.
Body
WHEREAS, Ordinance No. 10-12-6, adopted December 6, 2010, by the St. Charles Parish Council, approved and authorized the execution of a contract with Max Foote Construction for S080501-6 Destrehan Regional WWTP H2S System & Secondary Wet Well in the amount of $1,070,000.00; and,
WHEREAS, Ordinance No. 11-11-16, adopted November 21, 2011, by the St. Charles Parish Council, approved and authorized the execution of Change Order No.1 for parish project S080501-6 Destrehan Regional WWTP H2S System & Secondary Wet Well to increase the contract amount by $49,869.00 and increase the contract time by 38 days; and,
WHEREAS, it is necessary to amend the contract for final balancing of all items resulting in a decrease to the contract amount by $89,747.00 and increasing the contract time by 73 days.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS,
SECTION I. To approve and authorize the execution of Change Order No. 2(Final) for Parish Project No. S080501-6, Destrehan Regional WWTP H2S System & Secondary Wet Well to decrease the contract amount by $89,747.00 and increase the contract time by 73 days.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
SECTION III. St. Charles Parish considers the project complete and accepts all equipment installations, repairs, and modifications installed during execution of the project.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this _____ day of ___________, 2012,
to becom...
Click here for full text