2012-0079
INTRODUCED BY: V.J. ST. PIERRE, JR., PARISH PRESIDENT
(DEPARTMENT OF WATERWORKS)
ORDINANCE NO.
Title
An ordinance to approve and authorize the execution of Change Order No. 3 and Final for the East Bank Water Treatment Plant Upgrade to increase the contract time by 50 calendar days and to decrease the contract amount by $100.00.
Body
WHEREAS, Ordinance No. 08-9-7 adopted September 22, 2008, by the St. Charles Parish Council, approved and authorized the execution of a contract with M.R. Pittman Group, L.L.C. for the East Bank Water Treatment Plant Upgrade in the amount of $26,460,000.00; and,
WHEREAS, it is now necessary to increase the contract time by 50 calendar days and to decrease the contract amount by $100.00.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. (3) and Final for the East Bank Water Treatment Plant Upgrade to increase the contract time by 50 calendar days and to decrease the contract amount by $100.00 is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this day of , 2012, to become effective five (5) days after publication in the Official Journal.
CHAIRMAN:
SECRETARY:
DLVD/PARISH PRESIDENT:
APPROVED: DISAPPROVED:
PARISH PRESIDENT:
RETD/SECRETARY:
AT: RECD BY: