logo  ST. CHARLES PARISH, LA
File #: 2012-0150    Version: 1 Name: C.O. No. 2 - (Final) for Parish Project No. P090904, Engineers Canal Pump Station Bar Screen Cleaner Project
Type: Ordinance Status: Enacted
File created: 4/9/2012 In control: Parish Council
On agenda: Final action: 4/23/2012
Enactment date: 4/23/2012 Enactment #: 12-4-14
Title: An ordinance approving and authorizing the execution of Change Order No. 2 - (Final) for Parish Project No. P090904, Engineers Canal Pump Station Bar Screen Cleaner Project to decrease the contract amount by $6,660.00.
Sponsors: V.J. St. Pierre Jr., Department of Public Works
Indexes: DRO (Engineers Canal Pump Station Bar Screen Cleaners)
Attachments: 1. 2012-0150 Change Order-F, 2. 2012-0150 Final Ord 12-4-14 with Change Order
Related files: 2012-0034, 2022-0173, 2018-0339, 2021-0336, 2021-0218, 2014-0437, 2009-0420, 2019-0184, 2011-0164, 2009-0156
2012-0150
INTRODUCED BY: V.J. ST. PIERRE, JR., PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. _____
Title
An ordinance approving and authorizing the execution of Change Order No. 2 - (Final) for Parish Project No. P090904, Engineers Canal Pump Station Bar Screen Cleaner Project to decrease the contract amount by $6,660.00.
Body
WHEREAS, Ordinance No. 11-5-3 adopted May 2, 2011, by the St. Charles Parish Council, approved and authorized the execution of a contract with Sealevel Construction, Inc. for Parish Project No. P090904, Engineers Canal Pump Station Bar Screen Cleaner Project in the amount of $1,432,981.00; and,
WHEREAS, Ordinance No. 12-1-11 adopted January 23, 2012, by the St. Charles Parish Council, approved and authorized the execution of a contract with Sealevel Construction, Inc. for Parish Project No. P090904, Engineers Canal Pump Station Bar Screen Cleaner Project to decrease the contract amount by $68,792.15 and increase the contract time by three (3) days; and,
WHEREAS, the decrease in contract amount resulted from the net decrease of one line item in the amount of $6,660.00.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. 2 - (Final) for Parish Project No. P090904, Engineers Canal Pump Station Bar Screen Cleaner Project to decrease the contract amount by $6,660.00 is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:




And the ordinance was declared adopted this _____ day of ____________, 2012, to become effective five (5) days after publication in the Official Journal.


CHAIRMAN:______________________________________________
SECRETARY:_____________________________________________
DLVD/PARISH PRESIDENT:_________________________________
APPROVED:______________ DISAPPROVED:_...

Click here for full text