File #: 2009-0333    Version: 1 Name: Change Order No. 1 for Parish Project No. P070701, Maryland Drive Bridge Crossing, to add a line item for 10-Inch Depth Portland Cement Concrete Pavement and to increase the contract amount by $35,729.22
Type: Ordinance Status: Enacted
File created: 8/17/2009 In control: Parish Council
On agenda: Final action: 9/8/2009
Enactment date: 9/8/2009 Enactment #: 09-9-13
Title: An ordinance approving and authorizing the execution of Change Order No. 1 for Parish Project No. P070701, Maryland Drive Bridge Crossing, to add a line item for 10-Inch Depth Portland Cement Concrete Pavement and to increase the contract amount by $35,729.22.
Sponsors: V.J. St. Pierre Jr., Department of Public Works
Indexes: DRO (Maryland Drive Bridge Crossing)
Attachments: 1. 2009-0333 Change Order-F, 2. 2009-0333 Final Ord 09-9-13 with Change Order
Related files: 2007-0238, 2009-0099, 2010-0219, 2010-0235
2009-0333
INTRODUCED BY: V.J. St. Pierre, JR., PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.
Title
An ordinance approving and authorizing the execution of Change Order No. 1 for Parish Project No. P070701, Maryland Drive Bridge Crossing, to add a line item for 10-Inch Depth Portland Cement Concrete Pavement and to increase the contract amount by $35,729.22.
Body
WHEREAS, Ordinance No. 09-4-4 adopted April 6, 2009 by the St. Charles Parish Council awarded construction of Parish Project No P070701, Maryland Drive Bridge Crossing, to Byron E. Talbot Contractors; and,
WHEREAS, the relocation of an Entergy power line has added an additional unforeseen expense which need to be accounted for; and,
WHEREAS, it is necessary to amend the contract to account for the relocation of the power lines and to address other minor changes made for successful completion of the project and adjust the original contract quantities with current quantities resulting in an increase to the contract amount by $35,729.22.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. To approve and authorize the execution of Change Order No. 1 for Parish Project No. No P070701, Maryland Drive Bridge Crossing, to increase the contract amount by $35,729.22.
SECTION II. That the Parish President is hereby authorized to execute said Change Order.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:




And the ordinance was declared adopted this _____ day of _________, 2009, to become effective five (5) days after this publication in the official journal.


CHAIRMAN:_________________________________________
SECRETARY:________________________________________
DLVD/PARISH PRESIDENT:____________________________
APPROVED:______________ DISAPPROVED:_____________

PARISH PRESIDENT:_________________________________
RETD/SECRETARY:__________________________________
AT:_______________ RECD BY: _____________________...