logo  ST. CHARLES PARISH, LA
File #: 2010-0256    Version: 1 Name: C.O. No. 1(Final) for Parish Project No. P070108 Schexnayder Pump Station Bar Screen Cleaner and Deck to decrease the contract amount by $25,141.00 and decrease the contract time by thirty three (33) days
Type: Ordinance Status: Enacted
File created: 7/26/2010 In control: Parish Council
On agenda: Final action: 8/9/2010
Enactment date: 8/9/2010 Enactment #: 10-8-1
Title: An ordinance approving and authorizing the execution of Change Order No. 1(Final) for Parish Project No. P070108 Schexnayder Pump Station Bar Screen Cleaner and Deck to decrease the contract amount by $25,141.00 and decrease the contract time by thirty three (33) days.
Sponsors: V.J. St. Pierre Jr., Department of Public Works
Indexes: DRO (Schexnayder Pump Station Bar Screen Cleaner and Deck)
Attachments: 1. P070108 Ordinance Cover Letter_Ruby.doc, 2. 2010-0256 Change Order-F, 3. 2010-0256 Final Ord 10-8-1 with Change Order
Related files: 2007-0081, 2009-0476
2010-0256
INTRODUCED BY: V.J. ST. PIERRE, JR., PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.
Title
An ordinance approving and authorizing the execution of Change Order No. 1(Final) for Parish Project No. P070108 Schexnayder Pump Station Bar Screen Cleaner and Deck to decrease the contract amount by $25,141.00 and decrease the contract time by thirty three (33) days.
Body
WHEREAS, Ordinance No. 09-12-5, adopted December 21, 2009, by the St. Charles Parish Council, approved and authorized the execution of a contract with BLD Services, LLC for Parish Project No. P070108 Schexnayder Pump Station Bar Screen Cleaner and Deck in the amount of $2,163,567; and,
WHEREAS, the decrease in contract amount resulted from the deletion of two line items in the amount of $77,400, decreasing three line items in the amount of $17,000, and increasing three line items in the amount of $69,259; and,
WHEREAS, the decrease in contract time was a result of excellent weather and contractor management of their schedule.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. 1(Final) for Parish Project No. P070108 Schexnayder Pump Station Bar Screen Cleaner and Deck to decrease the contract amount by $25,141.00 and decrease the contract time by thirty three (33) days is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:




And the ordinance was declared adopted this _____ day of ____________, 2010, to become effective five (5) days after publication in the Official Journal.



CHAIRMAN:______________________________________________
SECRETARY:_____________________________________________
DLVD/PARISH PRESIDENT:_________________________________
APPROVED:______________ DISAPPROVED:__________________

PARISH PRESIDENT:...

Click here for full text