logo  ST. CHARLES PARISH, LA
File #: 2016-0275    Version: Name: Contract w/Tasch Electric LLC.-generator modifications and transfer switch at the EOC Center in the amount of $297,000.00, Parish Project No. P160501
Type: Ordinance Status: Enacted
File created: 10/3/2016 In control: Parish Council
On agenda: 10/17/2016 Final action: 10/17/2016
Enactment date: Enactment #: 16-10-7
Title: An ordinance to approve and authorize the execution of a Contract with Ready Power, LLC., for generator modifications and transfer switch at the St. Charles Parish Emergency Operations Center at 15026 River Road in Hahnville, Base bid in the amount of $342,000.00, Parish Project No. P160501.
Sponsors: Lawrence 'Larry' Cochran, Department of Emergency Preparedness
Indexes: Em. Prep. (Dept. of) (Generator/Switch), Em. Prep. (Dept. of) (Grounding)
Attachments: 1. 2016-0275 Section 00500 Contract, 2. 2016-0275 Bid Tab, 3. 2016-0275 Contract and bid tab, 4. 2016-0275 Postponed Proposed Ord (8-1-16), 5. 2016-0275 Contract-F, 6. 2016-0275 Final Ord 16-10-7 with Contract, 7. 2016-0275 Notice of Contract-F, 8. 2016-0275 Completion-F
Related files: 2016-0182, 2015-0316, 2013-0482, 2013-0481, 2009-0363, 2015-0050, 2011-0374, 2011-0309, 2010-0299, 2009-0442, 2010-0098, 2012-0394, 2013-0085, 2013-0198, 2019-0269, 2019-0296

2016-0275

INTRODUCED BY:                     LARRY COCHRAN, PARISH PRESIDENT

                                                               (DEPARTMENT OF EMERGENCY PREPAREDNESS)

ORDINANCE NO.                                                                 

Title

An ordinance to approve and authorize the execution of a Contract with Ready Power, LLC., for generator modifications and transfer switch at the St. Charles Parish Emergency Operations Center at 15026 River Road in Hahnville, Base bid in the amount of $342,000.00, Parish Project No. P160501.

Body

WHEREAS,                     sealed bids were received by St. Charles Parish on June 28, 2016, for Parish Project No. P160501; and,

WHEREAS,                     Huseman and Associates Consulting Engineers, Jason Chauvin, PE, the Engineer for said project, has reviewed the bids and recommended that the Contract be awarded to the low bidder, Ready Power, LLC, in the amount of $342,000.00; and,

WHEREAS,                     it is in the best interest of St. Charles Parish to award the Base Bid (Parish Project No. P160501), for modifying the generators and adding a transfer switch to the Emergency Operations Center.

THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:

SECTION I.                     That the bid of Ready Power LLC, for the construction of Parish Project No. P160501, is hereby approved and accepted in the amount of $342,000.00.

SECTION II.                     That the Parish President is hereby authorized to execute said contract on behalf of St. Charles Parish.

The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:

 

 

 

 

And the ordinance was declared adopted this            day of                       , 2016, to become effective five (5) days after publication in the Official Journal.

 

 

CHAIRMAN:                                                                                                                               

SECRETARY:                                                                                                                               

DLVD/PARISH PRESIDENT:                                                                                     

APPROVED:                         DISAPPROVED:                                           

 

PARISH PRESIDENT:                                                                                                          

RETD/SECRETARY:                                                                                                          

AT:                              RECD BY: