2000-0515
INTRODUCED BY: ALBERT D. LAQUE, PARISH PRESIDENT
(DEPARTMENT OF WASTEWATER)
ORDINANCE NO.
Title
An ordinance approving and authorizing the execution of Change Order No. Two (2) for the Bayou Gauche Pump Station and Force Main Project to increase the contract amount by $340,205.83 and to increase the contract time by 75 days.
Body
WHEREAS, Ordinance No. 99-10-12 adopted October 18, 1999 by the St. Charles Parish Council approved and authorized the execution of a contract with Fleming Construction Company, Inc. for the construction of the Bayou Gauche Pump Station and Force Main Project in the amount of $3,524,425.00, and
WHEREAS, Ordinance No. 00-8-6 adopted August 8, 2000 by the St. Charles Parish Council approved and authorized the execution of Change Order No. 1 that increased the contract amount by $113,879.37 and increased the contract time by 60 days to complete the missing section of the J.B Green Force Main Project, and
WHEREAS, Fleming Construction Company was required to change its force main installation method from open cut to directional bore in order to comply with the conditions of a Department of Transportation and Development permit thus adding additional cost to the job, and
WHEREAS, Fleming Construction Company was requested to complete the Hahnville Effluent Force Main which had been left unfinished by Bartlett Construction Company due to lack of servitude, and
WHEREAS, Fleming Construction Company was requested to complete the Hahnville Influent Force Main which had not been started by Bartlett Construction Company due to lack of servitude, and
WHEREAS, Fleming Construction Company was requested to complete 950 feet of gravity sewer inadvertently omitted from the Killona Lift Station and Force Main Project, and
WHEREAS, it is necessary to increase the contract amount by $340,205.83 and to increase the contract time by 75 calendar days to include the work to be performed as stated above.
NOW, THEREFORE, BE IT ORD...
Click here for full text