logo  ST. CHARLES PARISH, LA
File #: 2005-0225    Version: Name: Change Order No. 1 - Final for Parish Project No. P000303, Parish Wide Drainage Telemetry - Phase IIIA Lakewood Pump Station and Diane Pump Station
Type: Ordinance Status: Enacted
File created: 12/19/2005 In control: Parish Council
On agenda: Final action: 1/9/2006
Enactment date: 1/9/2006 Enactment #: 06-1-6
Title: An ordinance approving and authorizing the execution of Change Order No. One - (Final) for Parish Project No. P000303, Parish Wide Drainage Telemetry - Phase IIIA Lakewood Pump Station and Diane Pump Station, to decrease the contract amount by $9,720.00 and to increase the contract time by 77 days.
Sponsors: Albert D. Laque, Department of Public Works
Indexes: DRO (Telemetry Ph. IIIA, Lakewood Pump Station/Diane Pump Station)
Attachments: 1. 2005-0225 Change Order-F, 2. 2005-0225 Final Ord 06-1-6 with Change Order
Related files: 2005-0200, 2004-0284, 2004-0285, 2004-0286, 2000-0282, 2001-0010, 2005-0224, 2001-0218, 2001-0247, 2001-0444, 2003-0123
2005-0225
INTRODUCED BY:      ALBERT D. LAQUE, PARISH PRESIDENT
                  (DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.                   
Title
An ordinance approving and authorizing the execution of Change Order No. One - (Final) for Parish Project No. P000303, Parish Wide Drainage Telemetry - Phase IIIA Lakewood Pump Station and Diane Pump Station, to decrease the contract amount by $9,720.00 and to increase the contract time by 77 days.
Body
WHEREAS,      Ordinance No. 04-8-6 adopted August 2, 2004 by the St. Charles Parish Council awarded construction of Parish Project No. P000303, Parish Wide Drainage Telemetry - Phase IIIA Lakewood Pump Station and Diane Pump Station, to MMR Constructors, Inc.; and,
WHEREAS,      it is necessary to amend the contract to adjust the original contract quantities with actual quantities resulting in a decrease of $9,720.00 in the contract amount and an increase in the contract time by 77 calendar days.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I.      That the Administration is hereby authorized to execute Change Order No. One - (Final) for Parish Project No. P000303, Parish Wide Drainage Telemetry - Phase IIIA Lakewood Pump Station and Diane Pump Station, to decrease the contract amount by $9,720.00 and to increase the contract time by 77 calendar days.
SECTION II.      That the Parish President is hereby authorized to execute said Change Order.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
 
 
 
 
And the ordinance was declared adopted this            day of                       , 2006, to become effective five (5) days after publication in the Official Journal.
 
 
 
 
CHAIRMAN:                                     
SECRETARY:                                     
DLVD/PARISH PRESIDENT:                         
APPROVED:                         DISAPPROVED:             
 
PARISH PRESIDENT:                               
RETD/SECRETARY:                               
AT:                              RECD BY: