2009-0459
INTRODUCED BY: V.J. ST. PIERRE, JR, PARISH PRESIDENT
(GRANTS OFFICE)
ORDINANCE NO.
Title
An ordinance to approve and authorize the execution of a Contract with Barriere Construction Co., LLC for the St. Charles Parish East Bank Multi-Use Path, Phase II, State Project No. 744-45-0008, Federal Aid Project No. 4503(513) said Path to extend from Ormond Blvd. in Destrehan to West Harding Street in New Sarpy.
Body
WHEREAS, the Louisiana Department of Transportation and Development opened bids on September 30, 2009 for the above referenced project; and,
WHEREAS, the Department and the Parish have reviewed said bids and recommend that the project be awarded to the low bidder, Barriere Construction Co., L.L.C. in the amount of $265,577.10; and,
WHEREAS, it is the desire of the Parish Council to approve said Contract.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That the bid of Barriere Construction Co., L.L.C. for the St Charles Parish East Bank Multi-Use Path, Phase II, State Project No. 744-45-0008, Federal Aid Project No. 4503(513) is hereby approved and accepted in the amount of $265,577.10.
SECTION II. That the Parish President is hereby authorized to execute said Contract on behalf of the Parish of St. Charles.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this day of , 2009, to become effective five (5) days after publication in the Official Journal.
CHAIRMAN:
SECRETARY:
DLVD/PARISH PRESIDENT:
APPROVED: DISAPPROVED:
PARISH PRESIDENT:
RETD/SECRETARY:
AT: RECD BY: