Title: An ordinance to approve and authorize the execution of a contract with Digco Utility Construction, LP for the construction of Parish Project No. S080503, Priority Lift Stations & Force Mains, with a Bid in the amount of $1,510,228.00.
Sponsors: V.J. St. Pierre Jr., Department of Wastewater
Indexes: SPW (High Priority Sewer Lift Station Upgrades)
Attachments: 1. 2010-0446 Contract-F, 2. 2010-0446 Final Ord 11-1-1 with Contract, 3. 2010-0446 Completion-F
Related files: 2008-0422, 2009-0422, 2012-0198, 2012-0212, 2017-0308, 2018-0210
2010-0446
INTRODUCED BY:      V.J. ST. PIERRE, JR., PARISH PRESIDENT
                  (DEPARTMENT OF WASTEWATER)
ORDINANCE NO.  __________
Title
An ordinance to approve and authorize the execution of a contract with Digco Utility Construction, LP for the construction of Parish Project No. S080503, Priority Lift Stations & Force Mains, with a Bid in the amount of $1,510,228.00.
Body
WHEREAS,      sealed bids were received by St. Charles Parish on November 4, 2010 for Priority Lift Stations & Force Mains; and,
WHEREAS,      Environmental Engineering Services, Inc, Consulting Engineers for the Project, have reviewed the bids and recommend that the Bid of the Contract be awarded to the low bidder, Digco Utility Construction, LP, in the amount of $1,510,228.00.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
      SECTION I.      That the bid of Digco Utility Construction, LP, for the construction of St. Charles Parish Project No. S080503, Priority Lift Stations & Force Mains, be hereby approved and accepted, in the amount of $1,510,228.00.
      SECTION II.      That the Parish President is hereby authorized to execute said contract on behalf of St. Charles Parish.
Vote
      The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
 
 
 
 
      And the ordinance was declared adopted this ______ day of __________, 2011, to become effective five (5) days after publication in the Official Journal.
 
 
 
CHAIRMAN:______________________________________________
SECRETARY:_____________________________________________
DLVD/PARISH PRESIDENT:_________________________________
APPROVED:______________ DISAPPROVED:__________________
 
PARISH PRESIDENT:______________________________________
RETD/SECRETARY:_______________________________________