2012-0198
INTRODUCED BY: V.J. St. Pierre, JR., PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.
Title
An ordinance approving and authorizing the execution of Change Order No. 1 (Final) for Parish Project No S080503, Priority Lift Station & Force Mains, to balance the contract quantities with actual quantities resulting in a decrease of $78,307.60 and increase of 172 days.
Body
WHEREAS, Ordinance No. 11-1-1 adopted January 10, 2011 by the St. Charles Parish Council awarded construction of Parish Project No S080503, Priority Lift Station & Force Mains, to Digco Utility Construction LP; and,
WHEREAS, it is necessary to amend the contract to adjust the original contract quantities with actual quantities resulting in a decrease to the contract amount by $78,307.60 and increase of 172 days.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. 1 (Final) for Parish Project No. S080503, Priority Lift Station & Force Mains, to decrease the contract amount by $78,307.60 and increase the contract time by 172 days is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
SECTION III. St Charles Parish considers the project complete and accepts all equipment installations, repairs, and modifications installed during execution of the project.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this ______ day of __________, 2012, to become effective five (5) days after this publication in the official journal.
CHAIRMAN:
SECRETARY:
DLVD/PARISH PRESIDENT:
APPROVED: DISAPPROVED:
PARISH PRESIDENT:
RETD/SECRETARY:
AT: RECD BY: