2023-0307
INTRODUCED BY: MATTHEW JEWELL, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. ___________
Title
An ordinance approving and authorizing the execution of Change Order No. 1 for Road Maintenance 2022-23 (Project No. P220501), to increase the contract amount by $1,012,969.06 and increase the contract time by forty five (45) days.
Body
WHEREAS, Ordinance No. 22-7-2 adopted on July 5, 2022, by the St. Charles Parish Council, approved and authorized the execution of a Professional Services Agreement with Digital Engineering & Imaging, Inc., to perform planning services for the Road Maintenance 2022-23 (Project No. P220501), in the not to exceed amount of $316,728.72; and,
WHEREAS, Ordinance No. 23-6-9 adopted on June 19, 2023, by the St. Charles Parish Council for the execution of a Contract with Barriere Construction Co., LLC for Road Maintenance 2022-23 (Project No. P220501) in the amount of $2,499,902.45; and,
WHEREAS, Ordinance No. 23-8-8 adopted on August 28, 2023, by the St. Charles Parish Council, approved and authorized a Professional Services Agreement with Alpha Testing and Inspection, Inc., to perform testing services for Road Maintenance 2022-23 (Project No. P220501), in the not to exceed amount of $40,000.00; and,
WHEREAS, Ordinance No. 23-9-2 adopted on September 25, 2023, by the St. Charles Parish Council, approved and authorized Amendment No. 1 to the Professional Services Agreement with Digital Engineering & Imaging, Inc., to perform planning services for the Road Maintenance 2022-23 (Project No. P220501), in the total amount of $436,180.00; and,
WHEREAS, St. Charles Parish secured the funding to perform maintenance on an additional twenty nine (29) streets in the parish; and,
WHEREAS, the contract with Barriere Construction Co., LLC needs to be amended by change order to adjust the contract quantities with revised quantities resulting in an increase the contract amount by $1,012,969.06, and increase the contract time by fort...
Click here for full text