2021-0224
INTRODUCED BY: MATTHEW JEWELL, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS/WASTEWATER)
ORDINANCE NO.
Title
An ordinance approving and authorizing the execution of Change Order No. One (1) - FINAL for (Parish Project No. P190502), Schexnaydre Pump Station Improvements, to increase the contract amount by $43,529.73, and increase the contract time by 88 days.
Body
WHEREAS, Ordinance No. 20-8-10 adopted August 10, 2020 by the St. Charles Parish Council awarded construction of Parish Project No. P190502, Schexnaydre Pump Station Improvements, to Fleming Construction Company, L.L.C. in the amount of $654,016.00; and,
WHEREAS, it is necessary to increase the contract price by $43,529.73 and increase the number of days by 88 to balance project quantities with contract quantities. Final contract price will be $697,545.73.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. One (1) - FINAL for Schexnaydre Pump Station Improvements, (Parish Project No. P190502), to increase the contract amount by $43,529.73 and increase the contract time by 88 days is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this _______ day of __________, 2021, to become effective five (5) days after this publication in the official journal.
CHAIRMAN:
SECRETARY:
DLVD/PARISH PRESIDENT:
APPROVED : DISAPPROVED:
PARISH PRESIDENT:
RETD/SECRETARY:
AT: RECD BY: