WHEREAS, St. Charles Parish desires to have WWKS Project No. 59, Evangeline Road Waterline Upgrade, completed; and,
WHEREAS, this project requires professional services for the upgrade of approximately 5,000 feet of existing 4" and 6" water main to an 8" PVC water main including approximately 9 fire hydrants and 5 water valves; and,
WHEREAS, the construction will be partially funded by a Community Water Enrichment Fund Grant in the amount of $135,714.00; and,
WHEREAS, it is important that St. Charles Parish proceed with this project in order to protect the property and well-being of its citizens.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That the Engineering Services Contract with Danny J. Hebert, P.E., L.L.C. dba Civil & Environmental Consulting Engineers for the design of WWKS Project No. 59, Evangeline Road Waterline Upgrade is hereby approved.
SECTION II. That the Parish President is hereby authorized to execute said Engineering Services Contract on behalf of St. Charles Parish.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this day of , 2009, to become effective five (5) days after publication in the Official Journal.
CHAIRMAN:
SECRETARY:
DLVD/PARISH PRESIDENT:
APPROVED: DISAPPROVED:
PARISH PRESIDENT:
RETD/SECRETARY:
AT: RECD BY: