Title: An ordinance approving and authorizing the execution of Change Order No. 2 - Final for Parish Project No. S000601, Luling Oxidation Pond Wetland Assimilation, to decrease the contract amount by $2,000.00.
Sponsors: Albert D. Laque, Department of Wastewater
Indexes: SPW (Luling Oxidation Pond Wetlands Discharge)
Attachments: 1. 2006-0055 Change Order-F, 2. 2006-0055 Final Ord 06-2-7 with Change Order
Related files: 2005-0365, 2005-0364, 2003-0301, 2005-0301, 2006-0351, 2007-0329, 2010-0134, 2012-0142, 2013-0144, 2014-0067, 2015-0125, 1999-4905, 2000-0436, 2001-0322, 2002-0340, 2004-0356, 2009-0096, 2011-0135, 2016-0127, 2017-0020, 2017-0228, 2018-0013, 2018-0349, 2019-0249, 2019-0410, 2020-0250, 2020-0354, 2021-0157, 2021-0197, 2022-0061
2006-0055
INTRODUCED BY:      ALBERT D. LAQUE, PARISH PRESIDENT
                  (DEPARTMENT OF WASTEWATER)
ORDINANCE NO.__________
Title
An ordinance approving and authorizing the execution of Change Order No. 2 - Final for Parish Project No. S000601, Luling Oxidation Pond Wetland Assimilation, to decrease the contract amount by $2,000.00.
Body
WHEREAS,      Ordinance No. 05-12-38 adopted December 19, 2005 by the St. Charles Parish Council awarded construction of Parish Project No. S000601, Luling Oxidation Pond Wetland Assimilation, to Fleming Construction Company, Inc.; and,
WHEREAS,      Ordinance No. 05-12-39 adopted December 19, 2005 approved and authorized the execution of Change Order No. 1 to decrease the original contract amount by $21,400.00; and,
WHEREAS,      it is necessary to amend the contract to adjust the original contract quantities with actual quantities resulting in a decrease of $2,000.00 in the contract amount.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
      SECTION I.      To approve and authorize the execution of Change Order No. 2 - Final for Parish Project No. S000601, Luling Oxidation Pond Wetland Assimilation, to decrease the contract amount by $2,000.00.
      SECTION II.      That the Parish President is hereby authorized to execute said Change Order.
Vote
      The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
 
 
 
 
      And the ordinance was declared adopted this ______ day of __________, 2006, to become effective five (5) days after publication in the Official Journal.
2006-0055 C. O. No. 2 Luling Oxidation Pond
 
 
CHAIRMAN:______________________________________________
SECRETARY:_____________________________________________
DLVD/PARISH PRESIDENT:_________________________________
APPROVED:______________ DISAPPROVED:__________________
 
PARISH PRESIDENT:______________________________________
RETD/SECRETARY:_______________________________________
AT:_______________ RECD BY: _____________________________