2000-0491
INTRODUCDED BY: ALBERT D. LAQUE, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. _____________
Title
An ordinance approving and authorizing the execution of Change Order No. Two (2) for Parish Project No. P960309 Davis-Barton Drainage Improvements for the West Bank Drainage Improvements to increase the contract time by 27 calendar days.
Body
WHEREAS, Ordinance No. 98-9-5 adopted September 8, 1998 by the St. Charles Parish Council, approved and authorized the execution of a contract with Civil Construction Contractors Inc. for the construction of Davis-Barton Drainage Improvements for the West Bank Drainage Improvements in the amount of $1,725,120.00; and
WHEREAS, that an Ordinance No. 99-9-12 adopted September 7, 1999 approved and authorized the execution of Change Order No. One (1) for the Davis-Barton Drainage Improvements for the West Bank Drainage Improvements to increase the contract amount by $100,279.00 and increase the contract time by 45 calendar days; and
WHEREAS, that it is necessary to increase the original contract time by 27 calendar days to allow the contractor to receive his full retainage.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS,
SECTION I. That Change Order No. Two (2) to the contract for the Davis-Barton Drainage Improvements to increase the time by 27 calendar days is hereby approved.
SECTION II. That the Parish President is hereby authorized to execute said Change Order.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this _____ day of ___________, 2000,
to become effective five (5) days after publication in the Official Journal.
CHAIRMAN:______________________________________________
SECRETARY:_____________________________________________
DLVD/PARISH PRESIDENT:_________________________________
APPROVED:______________ DISAPPROVED:__________________
PARISH PRESIDENT:______________...