logo  ST. CHARLES PARISH, LA
File #: 2017-0010    Version: 1 Name: Acquire perpetual servitude - property identified as Parcel 1-1 in Hahnville, LA, to be used for the installation of a 14” sewerage pipeline in connection with Parish Project Killona Force Main Extension (S030101)
Type: Ordinance Status: Enacted
File created: 1/9/2017 In control: Parish Council
On agenda: 1/23/2017 Final action: 1/23/2017
Enactment date: Enactment #: 17-1-7
Title: An ordinance to approve and authorize the Parish President to acquire a perpetual servitude over, through, along, and across property identified as Parcel 1-1 in Hahnville, LA, which property is more particularly described in the Grant of Servitude attached hereto and made a part hereof, said property is to be used for the installation of a 14" sewerage pipeline in connection with Parish Project Killona Force Main Extension (S030101).
Sponsors: Lawrence 'Larry' Cochran, Department of Wastewater
Indexes: Legal Services (Dept. of), SPW (Killona Force Main)
Attachments: 1. 2017-0010 FINAL.SERVITUDE.forward to Council.1.6.17, 2. 2017-0010 Servitude-F, 3. 2017-0010 Final Ord 17-1-7 with Servitude
Related files: 2017-0009, 2016-0303, 2015-0149, 2015-0161, 2016-0230, 2016-0251, 2013-0410, 2018-0111, 2017-0061, 2003-0369, 2017-0080, 2018-0079
2017-0010
INTRODUCED BY: LARRY COCHRAN, PARISH PRESIDENT
(DEPARTMENT OF WASTEWATER)
ORDINANCE NO. ___________
Title
An ordinance to approve and authorize the Parish President to acquire a perpetual servitude over, through, along, and across property identified as Parcel 1-1 in Hahnville, LA, which property is more particularly described in the Grant of Servitude attached hereto and made a part hereof, said property is to be used for the installation of a 14" sewerage pipeline in connection with Parish Project Killona Force Main Extension (S030101).
Body
WHEREAS, the sewer line extending from the Killona area along LA Highway 3127 towards LA Highway 3160 to the St. Charles Parish Wastewater Treatment Plant in Hahnville, St. Charles Parish, Louisiana has a history of problems competing with the sewer line extending along LA Highway 3127 coming from the other direction of I-310; and,
WHEREAS, a force main was designed to carry sewage conveyed by the line coming from the Killona area directly to the Hahnville Wastewater Treatment Plant to eliminate this competition; and,
WHEREAS, the proposed force main requires the acquisition of a perpetual servitude ten feet (10') in width over, through, along, and across Parcel 1-1 in in Section 10, Township 13 South - Range 20 East, Hahnville, St. Charles Parish, Louisiana, described in the Grant of Servitude attached hereto, from Richard Weil, John Weil, Maureen Weil Stein, George Kantor and/or all other owners of record, as their interests may appear; and,
WHEREAS, the force main project and the acquisition of the hereinafter described servitude is in furtherance of the public's best interest and purpose, and is in satisfaction of a public need.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That the Parish President is hereby authorized to purchase at a price not to exceed its appraised value of $200.00 the property more particularly described in the Grant of Servitude attached hereto and made a part h...

Click here for full text