logo  ST. CHARLES PARISH, LA
File #: 2014-0318    Version: 1 Name: Contract with Barriere Construction Co., LLC for Road Maintenance 2014, with Base Bid and Alternate No. 1
Type: Ordinance Status: Enacted
File created: 9/15/2014 In control: Parish Council
On agenda: 10/6/2014 Final action: 10/6/2014
Enactment date: Enactment #: 14-10-8 AMENDED
Title: An ordinance to approve and authorize the execution of a contract with Barriere Construction Co., LLC for the construction of Parish Project No. P111002-15, Road Maintenance 2014, with Base Bid and Alternate No. 1, in the amount of $1,265,580.00.
Sponsors: V.J. St. Pierre Jr., Department of Public Works
Indexes: DRO (Road Overlay 2014)
Attachments: 1. 2014-0318 MX-M283N_20140911_153140, 2. 2014-0318 Contract-F, 3. 2014-0318 Final Ord 14-10-8 with Contract, 4. 2014-0318 Notice of Contract-F, 5. 2014-0318 Completion-F, 6. 2014-0318 Acceptance-F
Related files: 2017-0112, 2016-0282, 2013-0177, 2011-0348, 2016-0037, 2015-0103, 2014-0317, 2014-0065, 2015-0265, 2012-0299, 2013-0301, 2015-0092
2014-0318
INTRODUCED BY:      V.J. ST. PIERRE, JR., PARISH PRESIDENT
                  (DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. ____________
title
An ordinance to approve and authorize the execution of a contract with Barriere Construction Co., LLC for the construction of Parish Project No. P111002-15, Road Maintenance 2014, with Base Bid and Alternate No. 1, in the amount of $1,265,580.00.
body
WHEREAS,      sealed bids were received by St. Charles Parish on August 28, 2014 for Road Maintenance 2014; and,
WHEREAS,      GEC, Inc, Consulting Engineers for the Project, have reviewed the bids and recommend that the Base Bid and Alternate No. 1, of the Contract be awarded to the low bidder, Barriere Construction Co., LLC, in the amount of $1,265,580.00.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
      SECTION I.      That the bid of Barriere Construction Co., LLC, for the construction of St. Charles Parish Project No. P111002-15, Road Maintenance 2014, be hereby approved and accepted, in the amount of $1,265,580.00.
      SECTION II.      That the Parish President is hereby authorized to execute the said contract documents on behalf of St. Charles Parish.
      The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
 
 
 
 
      And the ordinance was declared adopted this ______ day of __________, 2014,
to become effective five (5) days after publication in the Official Journal.
 
 
 
CHAIRMAN:______________________________________________
SECRETARY:_____________________________________________
DLVD/PARISH PRESIDENT:_________________________________
APPROVED:______________ DISAPPROVED:__________________
 
 
PARISH PRESIDENT:______________________________________
RETD/SECRETARY:_______________________________________
AT:_______________RECD BY: _____________________________