File #: 1999-4889    Version: Name: Change Order 4 - Sewer Collection Skips - Phase IV Improvements
Type: Ordinance Status: Enacted
File created: 9/7/1999 In control: Parish Council
On agenda: Final action: 9/20/1999
Enactment date: 9/20/1999 Enactment #: 99-9-28
Title: An ordinance to approve and authorize the execution of Change Order No. Four (4) for the Sewer Collection Skips – Phase IV Improvements to decrease the contract amount by $33,496.22 and to increase the contract time by 79 calendar days.
Sponsors: Chris A. Tregre, Department of Wastewater
Indexes: SPW (Sewer Skips Ph. IV)
Attachments: 1. CO4 Sewer Skips Phase 4-revised, 2. CO4 Sewer Skips Phase 4, 3. 1999-4889 Change Order-F, 4. 1999-4889 Final Ord 99-9-28 with Change Order
Related files: 1999-4965
1999-4889
INTRODUCED BY: CHRIS A. TREGRE, PARISH PRESIDENT
(DEPARTMENT OF WASTEWATER)
ORDINANCE NO. ____________
Title
An ordinance to approve and authorize the execution of Change Order No. Four (4) for the Sewer Collection Skips – Phase IV Improvements to decrease the contract amount by $33,496.22 and to increase the contract time by 79 calendar days.
Body
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Ordinance No. 98-1-6 adopted January 5, 1998, by the St. Charles Parish Council, approved and authorized the execution of a contract with Bartlett Construction, Inc. for the construction of the Sewer Collection Skips – Phase IV Improvements in the amount of $1,128,503.00; and,
SECTION II. That Ordinance No. 98-4-5 adopted April 6, 1998, by the St. Charles Parish Council, approved and authorized the execution of Change Order No. One (1) for the Sewer Collection Skips – Phase IV Improvements Contract to increase the contract time by 45 calendar days; and,
SECTION III. That Ordinance No. 98-6-5 adopted June 1, 1998, by the St. Charles Parish Council, approved and authorized the execution of Change Order No. Two (2) for the Sewer Collection Skips – Phase IV Improvements Contract to increase the contract amount by $10,000.00; and,
SECTION IV. That Ordinance No. 99-3-8 adopted March 8, 1999, by the St. Charles Parish Council, approved and authorized the execution of Change Order No. Three (3) for the Sewer Collection Skips – Phase IV Improvements Contract to decrease the contract amount by $28,415.04 and to increase the contract time by 41 calendar days; and,
SECTION IV. That it is necessary to decrease the contract amount by $33,496.22 and to increase the contract time by 79 calendar days.
NOW, THEREFORE, BE IT ORDAINED, THAT WE, THE MEMBERS OF THE ST. CHARLES PARISH COUNCIL, do hereby approve and authorize the execution of Change Order No. Three (3) to the contract for the Sewer Collection Skips – Phase IV Improvements, to decrease t...