An ordinance to approve and authorize the execution of Change Order No. Four (4) for the Sewer Collection Skips – Phase IV Improvements to decrease the contract amount by $33,496.22 and to increase the contract time by 79 calendar days.
Body
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Ordinance No. 98-1-6 adopted January 5, 1998, by the St. Charles Parish Council, approved and authorized the execution of a contract with Bartlett Construction, Inc. for the construction of the Sewer Collection Skips – Phase IV Improvements in the amount of $1,128,503.00; and,
SECTION II. That Ordinance No. 98-4-5 adopted April 6, 1998, by the St. Charles Parish Council, approved and authorized the execution of Change Order No. One (1) for the Sewer Collection Skips – Phase IV Improvements Contract to increase the contract time by 45 calendar days; and,
SECTION III. That Ordinance No. 98-6-5 adopted June 1, 1998, by the St. Charles Parish Council, approved and authorized the execution of Change Order No. Two (2) for the Sewer Collection Skips – Phase IV Improvements Contract to increase the contract amount by $10,000.00; and,
SECTION IV. That Ordinance No. 99-3-8 adopted March 8, 1999, by the St. Charles Parish Council, approved and authorized the execution of Change Order No. Three (3) for the Sewer Collection Skips – Phase IV Improvements Contract to decrease the contract amount by $28,415.04 and to increase the contract time by 41 calendar days; and,
SECTION IV. That it is necessary to decrease the contract amount by $33,496.22 and to increase the contract time by 79 calendar days.