2024-0380
INTRODUCED BY: MATTHEW JEWELL, PARISH PRESIDENT
(DEPARTMENT OF WASTEWATER)
ORDINANCE NO. ___________
Title
An ordinance approving and authorizing the execution of a Professional Services Agreement with Kyle Associates, LLC, to perform engineering services for Turtle Pond Force Main Replacement (Project No. S241002), in the not to exceed amount of $412,827.00.
Body
WHEREAS, St. Charles Parish desires to replace the existing Turtle Pond lift station and force main to discharge sewerage directly to the existing Destrehan Wastewater Treatment Plant; and,
WHEREAS, the existing lift station's force main currently discharges at Rue Landry lift station which has become overloaded with flow on a normal basis; and,
WHEREAS, replacement of the force main will allow for reassessment and design of said force main to determine necessary size for future growth of the area; and,
WHEREAS, St. Charles Parish and Kyle Associates, LLC, have mutually agreed upon a not to exceed amount of $412,827.00 to complete the work of design, with the exception of supplemental fees of surveying, geotechnical and permitting to be determined during the conceptual phase of design; and,
WHEREAS, the attached Professional Services Agreement between St. Charles Parish and Kyle Associates, LLC, describes the details of the proposed services and compensation.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That the Professional Services Agreement between St. Charles Parish and Kyle Associates, LLC, to perform engineering services for the Turtle Pond Force Main Replacement (Project No. S241002), in the amount not to exceed $412,827.00, is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Agreement on behalf of St. Charles Parish.
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this _______ day of ______...
Click here for full text