logo  ST. CHARLES PARISH, LA
File #: 2023-0140    Version: 1 Name: Contract w/Barriere Construction, Co., LLC for Road Maintenance 2022-23 (Project No. P220501)
Type: Ordinance Status: Enacted
File created: 6/5/2023 In control: Parish Council
On agenda: 6/19/2023 Final action: 6/19/2023
Enactment date: Enactment #: 23-6-9 AMENDED
Title: An ordinance approving and authorizing the execution of a Contract with Barriere Construction Co., LLC for Road Maintenance 2022-23 (Project No. P220501) in the amount of $2,499,902.45.
Sponsors: Matthew Jewell, Department of Public Works
Indexes: DRO (Road Overlay 2022-23), Public Works (Dept. of)
Attachments: 1. 2023-0140 Section 0500 Contract, 2. 2023-0140 Notice of Intent to Award, 3. 2023-0140 Corporate Resolution, 4. 2023-0140 Bid Recommendation Letter, 5. 2023-0140 Bid Summary, 6. 2023-0140 Final Ord 23-6-9 with contract, 7. 2023-0140 Final Ord 23-6-9 with notice of contract, 8. 2023-0140 Notice of Contract, 9. 2023-0140 Recordation Documents, 10. 2023-0140 Certificate of Substantial Completion, 11. 2023-0140 Recordation Documents (2), 12. 2023-0140 Certificate of Final Acceptance, 13. 2023-0140 Recordation Documents F.A.
Related files: 2022-0180, 2024-0046, 2024-0204, 2023-0250, 2023-0216, 2023-0307
2023-0140
INTRODUCED BY: MATTHEW JEWELL, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. ____________
Title
An ordinance approving and authorizing the execution of a Contract with Barriere Construction Co., LLC for Road Maintenance 2022-23 (Project No. P220501) in the amount of $2,499,902.45.
Body
WHEREAS, Ordinance No. 22-7-2 adopted on July 5, 2022, by the St. Charles Parish Council approved and authorized the execution of a Professional Services Agreement with Digital Engineering & Imaging, Inc., to perform planning services for the Road Maintenance 2022-23 (Project No. P220501) in the not to exceed amount of $316,728.72; and,
WHEREAS, sealed bids were received by St. Charles Parish on May 23, 2023, Road Maintenance 2022-23 (Project No. P220501); and,
WHEREAS, Digital Engineering & Imaging, Inc. has reviewed the bids and recommends that the contract be awarded to the lowest responsive and responsible bidder, Barriere Construction Co., LLC, in the amount of $2,499,902.45.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That the bid of Barriere Construction Co., LLC for the construction of Road Maintenance 2022-23 (Project No. P220501) is hereby approved and accepted in the amount of $2,499,902.45.
SECTION II. That the Parish President is hereby authorized to execute said Contract on behalf of St. Charles Parish.
SECTION III. A final Notice of Contract shall be printed and filed in place of the Contract documents with the St. Charles Parish Clerk of Court and in the records of the St. Charles Parish Council.
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:




And the ordinance was declared adopted this ______ day of ___________, 2023, to become effective five (5) days after publication in the Official Journal.