2011-0393
INTRODUCED BY: V.J. St. Pierre, JR., PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.
Title
An ordinance approving and authorizing the execution of Change Order No. 1 for Parish Project No P090103-9, Road Maintenance 2011, to balance the contract quantities with actual quantities resulting in a decrease of $14,157.45.
Body
WHEREAS, Ordinance No. 11-8-2 adopted August 8, 2011 by the St. Charles Parish Council awarded construction of Parish Project No P090103-9, Road Maintenance 2011, to Barriere Construction Co, LLC; and,
WHEREAS, it is necessary to amend the contract to adjust the original contract quantities with actual quantities resulting in a decrease to the contract amount by $14,157.45.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. 1 for Parish Project No. P090103-9, Road Maintenance 2011, to decrease the contract amount by $14,157.45 is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this ______ day of __________, 2012, to become effective five (5) days after this publication in the official journal.
CHAIRMAN:
SECRETARY:
DLVD/PARISH PRESIDENT:
APPROVED : DISAPPROVED:
PARISH PRESIDENT:
RETD/SECRETARY:
AT: RECD BY: