File #: 2018-0181    Version: 1 Name: Change Order No. 1 (Final) for Parish Project No. P090201-6, Mimosa Avenue Culvert Replacement
Type: Ordinance Status: Enacted
File created: 7/9/2018 In control: Parish Council
On agenda: 7/23/2018 Final action: 7/23/2018
Enactment date: Enactment #: 18-7-11
Title: An ordinance approving and authorizing the execution of Change Order No. 1 (Final) for Parish Project No. P090201-6, Mimosa Avenue Culvert Replacement, to increase the contract amount by $6,045.44 and increase the contract time by seven days.
Sponsors: Lawrence 'Larry' Cochran, Department of Public Works
Indexes: DRO (Mimosa Culvert Replacement), Public Works (Dept. of)
Attachments: 1. 2018-0181 Change Order, 2. 2018-0181 Change Order-F, 3. 2018-0181 Final Ord with Change Order
Related files: 2012-0385, 2011-0391, 2009-0078, 2010-0230, 2011-0202, 2017-0367, 2011-0282, 2014-0389, 2015-0242, 2016-0246, 2017-0158, 2018-0334

2018-0181

INTRODUCED BY:                     LARRY COCHRAN, PARISH PRESIDENT

                                                               (DEPARTMENT OF PUBLIC WORKS)

ORDINANCE NO.                                                                

Title

An ordinance approving and authorizing the execution of Change Order No. 1 (Final) for Parish Project No. P090201-6, Mimosa Avenue Culvert Replacement, to increase the contract amount by $6,045.44 and increase the contract time by seven days.

Body

WHEREAS,                     Ordinance No. 17-11-8 adopted November 27, 2017, by the St. Charles Parish Council awarded construction of Parish Project No. P090201-6, Mimosa Avenue Culvert Replacement, to Fleming Construction Company, LLC in the amount of $341,000.00; and,

WHEREAS,                     it is necessary to amend the contract resulting in an increase in the contract price by $6,045.44 and an increase in the contract time by seven days.  Final Contract Price will be $347,045.44.

THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:

SECTION I.                     That Change Order No. 1 (Final) for Parish Project No. P090201-6, Mimosa Avenue Culvert Replacement, to increase the contract price by $6,045.44 and increase the contract time by seven days is hereby approved and accepted.

SECTION II.                     That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.

The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:

 

 

 

 

And the ordinance was declared adopted this              day of                      , 2018, to become effective five (5) days after publication in the Official Journal.

 

 

CHAIRMAN:______________________________________________

SECRETARY:_____________________________________________

DLVD/PARISH PRESIDENT:_________________________________

APPROVED:______________ DISAPPROVED:__________________

 

PARISH PRESIDENT:______________________________________

RETD/SECRETARY:_______________________________________

AT:_______________RECD BY: _____________________________