2018-0181
INTRODUCED BY: LARRY COCHRAN, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.
Title
An ordinance approving and authorizing the execution of Change Order No. 1 (Final) for Parish Project No. P090201-6, Mimosa Avenue Culvert Replacement, to increase the contract amount by $6,045.44 and increase the contract time by seven days.
Body
WHEREAS, Ordinance No. 17-11-8 adopted November 27, 2017, by the St. Charles Parish Council awarded construction of Parish Project No. P090201-6, Mimosa Avenue Culvert Replacement, to Fleming Construction Company, LLC in the amount of $341,000.00; and,
WHEREAS, it is necessary to amend the contract resulting in an increase in the contract price by $6,045.44 and an increase in the contract time by seven days. Final Contract Price will be $347,045.44.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. 1 (Final) for Parish Project No. P090201-6, Mimosa Avenue Culvert Replacement, to increase the contract price by $6,045.44 and increase the contract time by seven days is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this day of , 2018, to become effective five (5) days after publication in the Official Journal.
CHAIRMAN:______________________________________________
SECRETARY:_____________________________________________
DLVD/PARISH PRESIDENT:_________________________________
APPROVED:______________ DISAPPROVED:__________________
PARISH PRESIDENT:______________________________________
RETD/SECRETARY:_______________________________________
AT:_______________RECD BY: _____________________________