logo  ST. CHARLES PARISH, LA
File #: 2017-0287    Version: 1 Name: Change Order No. 1 to Amendment No. 5 as adopted by Ordinance No. 16-7-5 for WB Hurricane Protection Levee Professional Services
Type: Ordinance Status: Enacted
File created: 8/28/2017 In control: Parish Council
On agenda: 9/18/2017 Final action: 9/18/2017
Enactment date: Enactment #: 17-9-3
Title: An ordinance to approve and authorize the execution of Change Order No. 1 to Amendment No. 5 as adopted by Ordinance No. 16-7-5 for Project Number P080905-1D West Bank Hurricane Protection Levee Professional Services, as part of the West Bank Hurricane Protection Levee Project.
Sponsors: Lawrence 'Larry' Cochran, Department of Public Works
Indexes: Hurricane Protection Levee (WB)
Attachments: 1. 2017-0287 GCR CHANGE ORDER NO1, 2. 2017-0287 GCR Backup information, 3. 2017-0287 Final Ord 17-9-3 with Change Order
Related files: 2008-0417, 2011-0059, 2012-0355, 2014-0086, 2015-0171, 2016-0249, 2018-0322, 2020-0126, 2021-0055, 2022-0150
2017-0287
INTRODUCED BY: LARRY COCHRAN., PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.
Title
An ordinance to approve and authorize the execution of Change Order No. 1 to Amendment No. 5 as adopted by Ordinance No. 16-7-5 for Project Number P080905-1D West Bank Hurricane Protection Levee Professional Services, as part of the West Bank Hurricane Protection Levee Project.
Body
WHEREAS, the St. Charles Parish Council adopted Ordinance No. 08-10-6 on October 20, 2008 approving a professional services agreement with GCR, Inc. (formerly GCR & Associates, Inc.) for program management and right-of-way acquisition services for the Westbank Hurricane Protection Levee Project for a period of three years; and,
WHEREAS, the St. Charles Parish Council determined that services were still required for the progression of the project and adopted Ordinance No. 11-2-13 approving Amendment No. 1; Ordinance No. 12-10-6 approving Amendment No. 2; Ordinance No. 14-4-3 approving Amendment No. 3; Ordinance No. 15-6-7 approving Amendment No. 4; and Ordinance No. 16-7-5 approving Amendment No. 5.; and,
WHEREAS, Ordinance No. 16-7-5 adopted on July 5, 2016, by the St. Charles Parish Council, approved and authorized the execution of Amendment No. 5 to the Professional Service Contract Between GCR, INC., and ST. CHARLES PARISH which extended the contract time from May 1, 2016 through October 20, 2018 and allowed for a maximum compensation allowance of $275,000.00; and,
WHEREAS, the St. Charles Parish Council desires to approve Change Order No. 1 to Amendment No. 5 to increase the contract timeframe established therein by seventy two (72) days, so that it will now end on December 31, 2018 and increase maximum compensation limitation of the period established therein by $275,000.00 so that it is now set at $550,000.00.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. 1 to Amendment No. 5 as adopted by Ordinance No. 16-7-5 for Project Num...

Click here for full text