2022-0254
INTRODUCED BY: MATTHEW JEWELL, PARISH PRESIDENT
ORDINANCE NO.
Title
An ordinance approving and authorizing the execution of Change Order No. 6 for the Norco Library Renovation/Addition located at 590 Apple Street in Norco, to decrease the contract amount by $61,646.80.
Body
WHEREAS, Ordinance No. 18-1-10, adopted January 22, 2018, by the St. Charles Parish Council approved and authorized a construction contract with J.E. Franke Constructors, LLC, for Project No. P170601, for the renovation/addition of the Norco Branch Library in the amount of $1,110,025.00; and,
WHEREAS, Ordinance No. 18-6-2, adopted June 4, 2018, by the St. Charles Parish Council approved and authorized Change Order No. 1 to the contract with J.E. Franke Constructors, LLC, for the Norco Library Renovation/Addition to increase the contract amount by $11,755.00 and increase the contact time by five days; and,
WHEREAS, Ordinance No. 18-10-10, adopted October 15, 2018, by the St. Charles Parish Council approved and authorized Change Order No. 2 to the contract with J.E. Franke Constructors, LLC, for the Norco Library Renovation/Addition to increase the contract amount by $4,371.00 and increase the contact time by thirteen days; and,
WHEREAS, Ordinance No. 18-12-3, adopted December 10, 2018, by the St. Charles Parish Council approved and authorized Change Order No. 3 to the contract with J.E. Franke Constructors, LLC, for the Norco Library Renovation/Addition to decrease the contract amount by $151.00 and increase the contact time by 19 days; and,
WHEREAS, Ordinance No. 19-1-3, adopted January 7, 2019, by the St. Charles Parish Council approved and authorized Change Order No. 4 to the contract with J.E. Franke Constructors, LLC, for the Norco Library Renovation/Addition to increase the contract amount by $3,469.00 and increase the contact time by 10 days; and,
WHEREAS, Ordinance No. 19-2-8, adopted February 18, 2019, by the St. Charles Parish Council approved and authorized Change Ord...
Click here for full text