2011-0113
INTRODUCED BY: V.J. ST. PIERRE, JR., PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.
Title
An ordinance approving and authorizing the execution of Change Order No. 1(Final) for Parish Project No. P090701, Lakewood Pump Station Bar Screen Cleaner Project to decrease the contract amount by $66,380.00 and increase the contract time by five (5) days.
Body
WHEREAS, Ordinance No. 10-7-6, adopted July 12, 2010, by the St. Charles Parish Council, approved and authorized the execution of a contract with Sealevel Construction, Inc. for Parish Project No. P090701, Lakewood Pump Station Bar Screen Cleaner Project in the amount of $1,297,217.00; and,
WHEREAS, the decrease in contract amount resulted from the decrease of one line item in the amount of $67,900.00, and increasing one line item in the amount of $1,520.00; and,
WHEREAS, the increase in contract time was a result of days incurred to eliminate major subsurface ground obstructions identified while driving sheet pile.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS,
SECTION I. That Change Order No. 1(Final) for Parish Project No. P090701, Lakewood Pump Station Bar Screen Cleaner Project to decrease the contract amount by $66,380.00 and increase the contract time by five (5) days is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this _____ day of ___________, 2011,
to become effective five (5) days after publication in the Official Journal.
CHAIRMAN:_________________________________________
SECRETARY:________________________________________
DLVD/PARISH PRESIDENT:____________________________
APPROVED:______________ DISAPPROVED:_____________
PARISH PRESIDENT:_________________________________
RETD/SECRETARY:___________...