Title: An ordinance approving and authorizing the execution of Change Order No. One (1) for Parish Project No. P970703 Paul Maillard Road/Boutte Canal Crossing to increase the contract amount by $3,864.00 and to increase the contract time by 45 days.
Sponsors: Albert D. Laque, Department of Public Works
Indexes: DRO (Paul Maillard Road/Boutte Canal Crossing)
Attachments: 1. 2000-0152 Change Order-Final, 2. 2000-0152 Final Ord 00-4-8 with Change Order
2000-0152
INTRODUCED BY: ALBERT D. LAQUE, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. ________
Title
An ordinance approving and authorizing the execution of Change Order No. One (1) for Parish Project No. P970703 Paul Maillard Road/Boutte Canal Crossing to increase the contract amount by $3,864.00 and to increase the contract time by 45 days.
Body
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. Ordinance No. 99-9-4 adopted September 7, 1999 by the St.
Charles Parish Council, approved and authorized the execution of a contract with Civil Construction Contractors, Inc. for the construction of the Paul Maillard Road/Boutte Canal Crossing in the amount of $305,644.00.
SECTION II. That it is necessary to amend the contract to add 80 feet of 18 inch casing for a 10 inch water line and to increase the contract time by 45 calendar days to account for change order coordination and procurement of material.
SECTION III. That it is necessary to increase the contract amount by $3,864.00 and increase the contract time by 45 calendar days.
NOW, THEREFORE, BE IT ORDAINED, THAT WE THE MEMBERS OF ST. CHARLES PARISH COUNCIL, do hereby approve and authorize the execution of Change Order No. One (1) to the contract for the Paul Maillard Road/Boutte Canal Crossing and to increase the contract amount by $3,864.00 and increase the contract time by 45 calendar days.
BE IT FURTHER ORDAINED, that the Parish President is hereby authorized to execute this Change Order to the contract.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:




And the ordinance was declared adopted this ______ day of ____________, ____,
to become effective five (5) days after publication in the Official Journal.


CHAIRMAN:______________________________________________
SECRETARY:_____________________________________________
DLVD/PARISH PRESIDENT:_________________________________
APPROVED:______________ DIS...

Click here for full text