logo  ST. CHARLES PARISH, LA
File #: 2004-0060    Version: 1 Name: C.O. 2 - Final-Bayou Gauche Walking Track to decrease the contract amount by $58.36 and to increase the contract time by nineteen (19) days to balance quantities and negotiated items
Type: Ordinance Status: Enacted
File created: 2/2/2004 In control: Parish Council
On agenda: Final action: 2/16/2004
Enactment date: 2/16/2004 Enactment #: 04-2-8
Title: An ordinance to approve and authorize the execution of Change Order No. Two - Final for the Bayou Gauche Walking Track project number P020802 to decrease the contract amount by $58.36 and to increase the contract time by nineteen (19) days to balance quantities and negotiated items.
Sponsors: Albert D. Laque, Department of Public Works
Indexes: P and R (Dept. of) (Bayou Gauche)
Attachments: 1. 2004-0060 Change Order, 2. 2004-0060 Final Ord 04-2-8 with Change Order
Related files: 2003-0244, 2004-0059, 2009-0459
2004-0060
INTRODUCED BY: ALBERT D. LAQUE, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.:
Title
An ordinance to approve and authorize the execution of Change Order No. Two - Final for the Bayou Gauche Walking Track project number P020802 to decrease the contract amount by $58.36 and to increase the contract time by nineteen (19) days to balance quantities and negotiated items.
Body
WHEREAS, Ordinance No. 03-7-10, adopted on July 21, 2003 by the St. Charles Parish Council approved and authorized the execution of a contract with Civil Construction Contractors, Inc. for the construction of the Bayou Gauche Walking Track in the amount of $51,839.00; and,
WHEREAS, Ordinance No. 04-2-7, adopted on 2-16-04 by the St. Charles Parish Council approved and authorized the execution of Change Order No. One to increase the contract amount by $3,538.00 and to increase the contract time by twenty-three (23) days to complete the work; and,
WHEREAS, it is necessary to decrease the contract amount by $58.36 and to increase the contract time by nineteen (19) days to balance quantities and negotiated items.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. To approve and authorize the execution of Change Order No. Two - Final for the Bayou Gauche Walking Track project number P020802 to decrease the contract amount by $58.36 and to increase the contract time by nineteen (19) days to balance quantities and negotiated items.
SECTION II. That the Parish President is hereby authorized to execute said contract on behalf of the Parish of St. Charles.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:




And the ordinance was declared adopted this ______ day of __________, ____, to become effective five (5) days after publication in the Official Journal.




CHAIRMAN:______________________________________________
SECRETARY:_____________________________________________
DLVD/PARISH PRESIDENT:__...

Click here for full text