File #: 2005-0061    Version: 1 Name: Change Order No. 2 (Final) for Parish Project No. P030603 Hackberry Drainage Pump Station
Type: Ordinance Status: Enacted
File created: 2/21/2005 In control: Parish Council
On agenda: Final action: 3/21/2005
Enactment date: 3/21/2005 Enactment #: 05-3-5
Title: An ordinance approving and authorizing the execution of Change Order No. 2 (Final) for Parish Project No. P030603 Hackberry Drainage Pump Station to decrease the contract amount by $10,419.16 and to increase the contract time by 29 calendar days.
Sponsors: Albert D. Laque, Department of Public Works
Indexes: DRO (Hackberry Drg. Pump Station)
Attachments: 1. 2005-0061 Change Order-F, 2. 2005-0061 Final Ord 05-3-5 with Change Order
Related files: 2004-0259, 2004-0023, 2004-0162
2005-0061
INTRODUCED BY: ALBERT D. LAQUE, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.
Title
An ordinance approving and authorizing the execution of Change Order No. 2 (Final) for Parish Project No. P030603 Hackberry Drainage Pump Station to decrease the contract amount by $10,419.16 and to increase the contract time by 29 calendar days.
Body
WHEREAS, Ordinance No. 04-2-3 adopted February 2, 2004 by the St. Charles Parish Council, approved and authorized the execution of a contract with B&K Construction Co., Inc., for the construction of Hackberry Drainage Pump Station in the amount of $702,507.71; and
WHEREAS, Ordinance No. 04-7-6 adopted July 12, 2004 by the St. Charles Parish Council, approved and authorized the execution of Change Order No. 1 to increase the original contract amount by $27,786.83 and to increase the original contract time by 5 calendar days; and
WHEREAS, it is necessary to amend the contract to adjust the original contract quantities with actual quantities resulting in a decrease of $10,419.16 in the contract amount and a increase in the contract time by 29 calendar days.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. To approve and authorize the execution of Change Order No. 2 (Final) for Parish Project No. P030603, Hackberry Drainage Pump Station, to decrease the contract amount by $10,419.16 and to increase the contract time by 29 calendar days.
SECTION II. That the Parish President is hereby authorized to execute said Change Order.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:




And the ordinance was declared adopted this day of , ______,to become effective five (5) days after publication in the Official Journal.



CHAIRMAN:
SECRETARY:
DLVD/PARISH PRESIDENT:
APPROVED: DISAPPROVED:

PARISH PRESIDENT:
RETD/SECRETARY:
AT: ...

Click here for full text