2014-0261
INTRODUCED BY: V.J. St. Pierre, JR., PARISH PRESIDENT
(DEPARTMENT OF PARKS AND RECREATION)
ORDINANCE NO.
title
An ordinance approving and authorizing the execution of Change Order No. 2 (final) for the Renovations to Ormond Field RE-BID Project to add 30 additional days to the contract.
body
WHEREAS, Ordinance No. 13-9-11 adopted September 16, 2013 by the St. Charles Parish Council awarded construction of the Renovations to Ormond Field RE-BID Project to Dynamic Constructors, LLC; and,
WHEREAS, Ordinance No. 14-4-2 adopted April 7, 2014 by the St. Charles Parish Council authorized Change Order #1 to increase the contract by $73,616.35 and add an additional 49 days; and,
WHEREAS, It is necessary to amend the contract to add an additional 30 days due to multiple weather delays.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order Number 2 (final) for the Renovations to Ormond Field RE-BID Project to add 30 additional days to the contract is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this ______ day of __________, 2014, to become effective five (5) days after this publication in the official journal.
CHAIRMAN:_________________________________________
SECRETARY:________________________________________
DLVD/PARISH PRESIDENT:____________________________
APPROVED:______________ DISAPPROVED:_____________
PARISH PRESIDENT:_________________________________
RETD/SECRETARY:__________________________________
AT:_______________ RECD BY: ________________________