logo  ST. CHARLES PARISH, LA
File #: 2024-0158    Version: 1 Name: C.O. No. 3 for the SCP E. Dufresne Community Center Ida & Window Repairs, (Project No. EDCC 0322)
Type: Ordinance Status: Enacted
File created: 4/15/2024 In control: Parish Council
On agenda: 5/6/2024 Final action: 5/6/2024
Enactment date: Enactment #: 24-5-7
Title: An ordinance approving and authorizing the execution of Change Order No. 3 for the SCP E. Dufresne Community Center Ida & Window Repairs, (Project No. EDCC 0322), to increase the contract amount by $17,178.00 and increase the contract time by 125 days.
Sponsors: Matthew Jewell, General Government Buildings
Indexes: Community Center (SCP E Dufresne Community Center Ida and Window Repairs), Government Bldgs.
Attachments: 1. 2024-0158 EADCC Change Order number 3, 2. 2024-0158 Final Ord 24-5-7 with change order, 3. 2024-0158 Recordation Documents
Related files: 2023-0275, 2023-0127, 2023-0002
2024-0158
INTRODUCED BY: MATTHEW JEWELL, PARISH PRESIDENT
(GENERAL GOVERNMENT BUILDINGS)
ORDINANCE NO. __________
Title
An ordinance approving and authorizing the execution of Change Order No. 3 for the SCP E. Dufresne Community Center Ida & Window Repairs, (Project No. EDCC 0322), to increase the contract amount by $17,178.00 and increase the contract time by 125 days.
Body
WHEREAS, on March 25, 2022, the St. Charles Parish President and Meyer Engineers, LTD., executed a Professional Service Agreement to perform architectural and engineering services for said project in the lump sum amount of $148,981.00; and,
WHEREAS, Ordinance No. 23-1-8 adopted on January 23, 2023, by the St. Charles Parish Council, approved and authorized the execution of a contract with NFT Group LLC, for the SCP E. Dufresne Community Center Ida & Window Repairs, (Project No. EDCC 0322), in the amount of $1,144,000.00; and,
WHEREAS, Ordinance No. 23-6-4 adopted on June 5, 2023, by the St. Charles Parish Council, approved and authorized the execution of Change Order No. 1 for SCP E. Dufresne Community Center Ida & Window Repairs, (Project No. EDCC 0322), to increase the contract amount by $82,465.00 and increase the contract time by 9 days; and,
WHEREAS, Ordinance No. 23-10-6 adopted on October 23, 2023, by the St. Charles Parish Council, approved and authorized the execution of Change Order No. 2 for SCP E. Dufresne Community Center Ida & Window Repairs, (Project No. EDCC 0322), to increase the contract amount by $138,567.00 and increase the contract time by 60 days; and,
WHEREAS, the increase in the contract amount by $17,178.00 and increase the contract time by 125 days is a result in additional work items.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. 3 for the SCP E. Dufresne Community Center Ida & Window Repairs, (Project No. EDCC 0322), to increase the contract amount by $17,178.00 and increase the contract time by 125 days i...