File #: 2015-0253    Version: 1 Name: Contract with Sealevel Construction, Inc. for Willowridge Drainage Pump Station Project, as part of the West Bank Hurricane Protection Levee Project
Type: Ordinance Status: Enacted
File created: 7/20/2015 In control: Parish Council
On agenda: 8/3/2015 Final action: 8/3/2015
Enactment date: Enactment #: 15-8-5 AMENDED
Title: An ordinance to approve and authorize the execution of a Construction Contract with Sealevel Construction, Inc. for Project No. P080905-4A, State Project No. H.010102, Willowridge Drainage Pump Station Project, as part of the West Bank Hurricane Protection Levee Project, in the amount of $5,572,160.00.
Sponsors: V.J. St. Pierre Jr., Department of Public Works
Indexes: Floods, Highway Dept., Hurricane Protection Levee (WB - Willowridge)
Attachments: 1. 2015-0253 Contract-bid tabs, 2. 2015-0253 Contract-F, 3. 2015-0253 Final Ord 15-8-5 with Contract, 4. 2015-0253 Notice of Contract-F, 5. 2015-0253 Completion-F, 6. 2015-0253 Acceptance-F
Related files: 2011-0307, 2012-0084, 2012-0294, 2015-0116, 2015-0233, 2015-0234, 2016-0298, 2016-0387, 2017-0350, 2017-0411, 2018-0159
2015-0253
INTRODUCED BY: V.J. ST. PIERRE, JR., PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.
Title
An ordinance to approve and authorize the execution of a Construction Contract with Sealevel Construction, Inc. for Project No. P080905-4A, State Project No. H.010102, Willowridge Drainage Pump Station Project, as part of the West Bank Hurricane Protection Levee Project, in the amount of $5,572,160.00.
Body
WHEREAS, sealed bids were received by St. Charles Parish on June 23, 2015 for Project No. P080905-4A, State Project No. H.010102, Willowridge Drainage Pump Station Project; and,
WHEREAS, Burk-Kleinpeter, Inc., Michael G. Jackson, P.E., the Engineer for the Project, has reviewed the bids and recommended that the Contract be awarded to the lowest responsive bidder, Sealevel Construction, Inc. in the amount of $5,572,160.00; and,
WHEREAS, the Willowridge Drainage Pump Station Project, as part of the West Bank Hurricane Protection Levee Project, will provide flood protection to approximately 209 acres, 364 structures and 4 miles of public streets located in the Willowridge Estates subdivision area; and,
WHEREAS, the Willowridge Drainage Pump Station Project consists of the installation of a new Drainage Pump Station, intake channel and discharge over the recently installed Willowridge Levee system protecting Willowridge Estates subdivision area. The project includes the purchase and installation of three (3) 100 cfs pumps, new CMU electrical room, standby generator, station concrete structure, access road, intake channel and culvert, discharge piping and basin, screen cleaners, excavation of a retention area adjacent to the pump station and the filling of the levee gaps at Willowridge and Cypress Drives; and,
WHEREAS, Resolution No. 5930 on August 20, 2012, approved an Intergovernmental Agreement with the State of Louisiana Department of Transportation and Development (DOTD) under the Louisiana Statewide Flood Control Program to ...