2003-0197
INTRODUCED BY: ALBERT D. LAQUE, PARISH PRESIDENT
(DEPARTMENT OF WASTEWATER)
ORDINANCE NO.
Title
An ordinance to approve and authorize the execution of Change Order No. One - Final for the Willowridge 8-inch Sewer Force Main Replacement project number S021201 to decrease the contract amount by $4,394.00 and to decrease the contract time by 30 days to balance quantities and negotiated items.
Body
WHEREAS, Ordinance No. 03-4-6, adopted on April 7, 2003 by the St. Charles Parish Council approved and authorized the execution of a contract with D & O Contractors, Inc. for the replacement of a force main in the amount of $41,407.00; and,
WHEREAS, it is necessary to decrease the contract amount by $4,394.00 and to decrease the contract time by 30 days to balance quantities and negotiated items.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. To approve and authorize the execution of Change Order No. One - Final for the Willowridge 8-inch Sewer Force Main Replacement project number S021201 to decrease the contract amount by $4,394.00 and to decrease the contract time by 30 days to balance quantities and negotiated items.
SECTION II. That the Parish President is hereby authorized to execute said contract on behalf of the Parish of St. Charles.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this ______ day of __________, 2003,
to become effective five (5) days after publication in the Official Journal.
CHAIRMAN:______________________________________________
SECRETARY:_____________________________________________
DLVD/PARISH PRESIDENT:_________________________________
APPROVED:______________ DISAPPROVED:__________________
PARISH PRESIDENT:______________________________________
RETD/SECRETARY:_______________________________________
AT:_______________RECD BY: _____________________________