Skip to main content
logo  ST. CHARLES PARISH, LA
File #: 2025-0200    Version: 1 Name: Amendment No. 1 to Ordinance No. 21-8-14, which approved the Professional Services Agreement with Volkert, Inc. for the Evangeline Road & CN Railroad Box Culvert (Project No. P210701)
Type: Ordinance Status: Public Hearing
File created: 7/21/2025 In control: Parish Council
On agenda: 8/4/2025 Final action:
Enactment date: Enactment #:
Title: An ordinance approving and authorizing the execution of Amendment No. 1 to Ordinance No. 21-8-14, which approved the Professional Services Agreement with Volkert, Inc. for the Evangeline Road & CN Railroad Box Culvert (Project No. P210701), in the not to exceed amount of $202,712.50, increasing the overall contract value to $389,718.34.
Sponsors: Matthew Jewell, Department of Public Works
Attachments: 1. 2025-0200 Volkert, Inc. - Amendment - June 28, 2025, 2. 2025-0200 2025_3_24 Billable rates, 3. 2025-0200 Volkert, Inc. - Corporate Resolution - October 30, 2024
Related files: 2021-0214
2025-0200
INTRODUCED BY: MATTHEW JEWELL, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. ___________
Title
An ordinance approving and authorizing the execution of Amendment No. 1 to Ordinance No. 21-8-14, which approved the Professional Services Agreement with Volkert, Inc. for the Evangeline Road & CN Railroad Box Culvert (Project No. P210701), in the not to exceed amount of $202,712.50, increasing the overall contract value to $389,718.34.
Body
WHEREAS, Ordinance No. 21-8-14 adopted on August 23, 2021, by the St. Charles Parish Council. approved and authorized the execution of a Professional Services Agreement with Volkert, Inc., to perform engineering services for Evangeline Road & CN Railroad Box Culvert (Project No. P210701), in the not to exceed amount of $187,005.84; and,
WHEREAS, the utility conflicts both parallel and perpendicular to the railroad required much more in-depth coordination and design work to incorporate protection and/or avoidance of said conflicts to ensure railroad permitting was completed successfully, therefore justifying more funds be provided to Volkert, Inc. for the work; and,
WHEREAS, St. Charles Parish met with Volkert, Inc. and requested the scope be changed slightly to include leaving the sheet piles required for shoring in place permanently, requiring more design; and,
WHEREAS, with this Amendment St. Charles Parish and Volkert, Inc. have mutually agreed to reallocate the existing funds of $187,005.84 from the original agreement to appropriately match where the funds were spent; and,
WHEREAS, upon receipt of the Canadian National Railroad (CNRR) Permit, St. Charles Parish will bid this project, therefore requiring Resident Project Representative (RPR) services be added to the contract; and,
WHEREAS, St. Charles Parish and Volkert, Inc. have mutually agreed on a not to exceed price of $202,712.50 to complete the work, increasing the overall contract value to $389,718.34.