File #: 2015-0476    Version: 1 Name: C.O. No. 1 and final for the West Bank “B” Plant Clarifier Refurbishment (Project No. WWKS 72) to increase the contract time by 56 calendar days and to increase the contract amount by $13,005.93
Type: Ordinance Status: Enacted
File created: 12/14/2015 In control: Parish Council
On agenda: 1/12/2016 Final action: 1/12/2016
Enactment date: Enactment #: 16-1-10
Title: An ordinance to approve and authorize the execution of Change Order No. 1 and final for the West Bank "B" Plant Clarifier Refurbishment (Project No. WWKS 72) to increase the contract time by 56 calendar days and to increase the contract amount by $13,005.93.
Sponsors: V.J. St. Pierre Jr., Department of Waterworks
Indexes: WW (WB B-Plant Clarifier Refurbishment)
Attachments: 1. 2015-0476 CO West Bank B Plant Clarifier, 2. 2015-0476 Change Order-F, 3. 2015-0476 Final Ord 16-1-10 with Change Order
Related files: 2013-0013, 2013-0322, 2014-0063, 2015-0126

2015-0476

INTRODUCED BY:                     V.J. ST. PIERRE, JR., PARISH PRESIDENT

(DEPARTMENT OF WATERWORKS)

ORDINANCE NO                                                               

Title

An ordinance to approve and authorize the execution of Change Order No. 1 and final for the West Bank “B” Plant Clarifier Refurbishment (Project No. WWKS 72) to increase the contract time by 56 calendar days and to increase the contract amount by $13,005.93.

Body

WHEREAS,                     Ordinance No. 15-4-14 adopted April 20, 2015, by the St. Charles Parish Council, approved and authorized the execution of a contract with Pintail Contracting Services, LLC for the West Bank “B” Plant Clarifier Refurbishment (Project No. WWKS 72) in the amount of $265,499.96; and,

WHEREAS,                     it is now necessary to increase the contract time by 56 calendar days and to increase the contract amount by $13,005.93.

THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:

SECTION I.                     That Change Order No. One (1) and final for the West Bank “B” Plant Clarifier Refurbishment (Project No. WWKS 72) to increase the contract time by 56 calendar days and to increase the contract amount by $13,005.93 is hereby approved and accepted.

SECTION II.                     That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.

                     The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:

 

 

 

 

                     And the ordinance was declared adopted this ____ day of                       , 2016, to become effective five (5) days after publication in the Official Journal.

 

 

CHAIRMAN:_________________________________________

SECRETARY:________________________________________

DLVD/PARISH PRESIDENT:____________________________

APPROVED:______________ DISAPPROVED:_____________

 

PARISH PRESIDENT:_________________________________

RETD/SECRETARY:__________________________________

AT:_______________ RECD BY: ________________________