File #: 2011-0202    Version: 1 Name: Change Order No. 1(Final) for Michael Drive Drainage Improvements
Type: Ordinance Status: Enacted
File created: 6/6/2011 In control: Parish Council
On agenda: Final action: 6/20/2011
Enactment date: 6/20/2011 Enactment #: 11-6-16
Title: An ordinance approving and authorizing the execution of Change Order No. 1(Final) for Parish Project No. P090201-1 Michael Drive Drainage Improvements to decrease the contract amount by $17,675.00 and add forty six (46) days to the contract time.
Sponsors: V.J. St. Pierre Jr., Department of Public Works
Indexes: DRO (Culvert Replacement at Michael Dr.)
Attachments: 1. Change Order document Michael Dr.doc, 2. Michael drive Change Order Breakdown.pdf, 3. Cover Memo for Change Orders Michael Dr, 4. 2011-0202 Change Order-F, 5. 2011-0202 Final Ord 11-6-16 with Change Order
Related files: 2018-0334, 2009-0078, 2010-0230, 2017-0158, 2017-0367, 2018-0181, 2016-0246
2011-0202
INTRODUCED BY: V.J. ST. PIERRE, JR., PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. _____
Title
An ordinance approving and authorizing the execution of Change Order No. 1(Final) for Parish Project No. P090201-1 Michael Drive Drainage Improvements to decrease the contract amount by $17,675.00 and add forty six (46) days to the contract time.
Body
WHEREAS, Ordinance No. 10-7-5 adopted July 12, 2010, by the St. Charles Parish Council, approved and authorized the execution of a contract with Civil Construction Contractors, Inc. for Parish Project No. P090201-1 Michael Drive Drainage Improvements in the amount of $179,496.25; and,
WHEREAS, the decrease in contract amount resulted from the deletion of two line items in the amount of $33,135.00 and reducing one line item by $3,040.00 offsetting the addition of three line items in the amount of $18,500.00; and,
WHEREAS, the increase in contract time was a result of twelve days (12) for rain and thirty four days (34) for additional work.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS,
SECTION I. To approve and authorize the execution of Change Order No. 1(Final) for Parish Project No. Project No. P090201-1 Michael Drive Drainage Improvements to decrease the contract amount by $17,675.00 and increase the contract time by forty six (46) days.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:




And the ordinance was declared adopted this _____ day of ___________, 2011,
to become effective five (5) days after publication in the Official Journal.



CHAIRMAN:______________________________________________
SECRETARY:_____________________________________________
DLVD/PARISH PRESIDENT:_________________________________
APPROVED:______________ DISAPPROVED:__________________

PARISH PRESIDENT:________________...