Title: An ordinance approving and authorizing the execution of Change Order No. 1 (Final) for the St. Charles Parish Planning & Zoning Building Project #CD 2512 to increase the contract amount by $9,850.00 and increase the contract time by five days.
Sponsors: Lawrence 'Larry' Cochran, General Government Buildings
Indexes: Courthouse, Jail and Facilities (P&Z Bldg. Expansion), P and Z (Dept. of)
Attachments: 1. 2018-0295 Change Order, 2. 2018-0295 Final Ord 18-11-4 with change order
Related files: 2017-0407, 2017-0408, 2018-0127

2018-0295

INTRODUCED BY:                     LARRY COCHRAN, PARISH PRESIDENT

                                                               (GENERAL GOVERNMENT BUILDINGS)

ORDINANCE NO.                                                                 

Title

An ordinance approving and authorizing the execution of Change Order No. 1 (Final) for the St. Charles Parish Planning & Zoning Building Project #CD 2512 to increase the contract amount by $9,850.00 and increase the contract time by five days.

Body

WHEREAS,                     Ordinance No. 18-5-8 adopted May 21, 2018, by the St. Charles Parish Council awarded construction of the St. Charles Parish Planning & Zoning Building Project #CD 2512, to Frickey Brothers Construction in the amount of $507,000.00, and,

WHEREAS,                     it is necessary to amend the original contract to reflect those items fully described in Change Order No. 1 (Final) resulting in an increase in the contract price by $9,850.00 and an increase in the contract time by five days.  Final Contract Price will be $516,850.00.

THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:

                     SECTION I.                     That Change Order No. 1 (Final) for the St. Charles Parish Planning & Zoning Project to increase the contract amount by $9,850.00 and increase the contract time by five days is hereby approved and accepted.

                     SECTION II.                     That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.

The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:

 

 

 

 

And the ordinance was declared adopted this ____ day of ________, 2018, to become effective five (5) days after this publication in the official journal.

 

CHAIRMAN:_________________________________________

SECRETARY:________________________________________

DLVD/PARISH PRESIDENT:____________________________

APPROVED:______________ DISAPPROVED:_____________

 